contractors.fyi
Sign in

How long does a home addition permit take in Los Angeles?

In Los Angeles, the typical home addition permit took about 4 months (114 days) from application to issue, across 10,154 permits issued from September 2024 to September 2026. After the permit, the typical finished home addition took about 13 months (384 days) from permit to final inspection (7,414 finished of 10,398 permits issued from September 2022 to September 2024; 29% had no final inspection on record by September 2026).

4 monthsfrom application to permitMiddle half: 53 days to 8 months
13 monthsfrom permit to final inspectionMiddle half: 8 months to 19 months

The two steps

How long home additions take in Los Angeles, in daysApplication to permit issued: median 114 days, middle half 53 to 230 days, 10,154 permits; Permit issued to final inspection: median 384 days, middle half 242 to 580 days, 7,414 permits.Application to permit issued: about 4 monthsPermit issued to final inspection: about 13 months06 mo12 mo18 mo
Bars show the median; the line through each bar spans the middle half of jobs. The second step starts where the typical permit wait ends. The two steps come from different groups of permits, so they are not added up.
The numbers behind the chart
StepMedianMiddle halfPermitsPermits issued
Application to permit issuedabout 4 months53 days to about 8 months10,154September 2024 to September 2026
Permit to final inspectionabout 13 monthsabout 8 months to about 19 months7,414September 2022 to September 2024

Home addition contractors with the most finished jobs in Los Angeles

RankContractorFinished jobsContact
1Preferred Home Builders Inc
Canoga Park, licensed 26 years
26
Visit website
2Pampa Investment Inc
San Ysidro, licensed 22 years
18
Call (310) 774-6843
3Golden Patio Restoration
Woodland Hills, licensed 14 years
17
Visit website

See all 357 ranked home addition contractors

Get quotes from up to 3 licensed home addition contractors

Five quick questions. We send your request to up to 3 contractors who work near you, and email you who they are.

You decide who to hire. Your details go only to the contractors you pick. How we use your details

1. Where is the job?

We match contractors who work near it. We never ask for your street address.

2. What do you need?

Pick any that fit.

3. When do you want to start?
4. What is your rough budget?

A range is fine. It helps contractors reply with a real number.

5. Where should we send it?

Your contact details go only to who you pick here.

Sent. We have your request.

Over the next few days we email you up to 3 contractors who fit, and pass your request to them. Replies usually come within a few days.

Your job room keeps the request, your photos and every reply in one place, with an assistant that checks prices against city permits. Keep its link: it is the key to your job.

Open your job room

Permit wait by year issued

Year issuedJobsMedianMiddle half
20221,509about 5 months67 days to about 9 months
20235,097about 5 months60 days to about 10 months
20245,091about 4 months52 days to about 9 months
20255,352about 4 months51 days to about 8 months
20263,486about 4 months56 days to about 7 months

Why it takes this long

  • 2% of permits were issued the day they were applied for, and 14% within 30 days (10,154 permits).
  • 3 more permits issued in those dates carry no application date and are left out of the permit wait.
  • The longer step is building and inspection: about 4 months for the permit against about 13 months from permit to final, at the median.
  • 5% of finished jobs passed final inspection within 90 days of the permit.
  • Of the 10,398 permits issued from September 2022 to September 2024, 2,984 (29%) had no final inspection on record by September 2026. They may still be under way, dropped or never inspected; the records do not say which. They are left out of the build time; any of them that finishes will have taken more than two years, so counting them would make the typical time longer.

Days are counted between the dates on each city permit: submitted_date, issue_date; final: status 'Permit Finaled' or a certificate, dated by cofo_date or status_date. Median and middle half: half of the jobs took longer than the median; the middle half runs from the 25th to the 75th percentile. A figure is shown only when it rests on 30 or more permits. Kinds of work are sorted by the same rules as our contractor lists. Source: City of Los Angeles, Building Permits Issued from 2020 to Present, read 2026-09-24. The same figures as data: addition.json.