How long does an ADU permit take in Los Angeles?
In Los Angeles, the typical ADU permit took about 4 months (119 days) from application to issue, across 15,650 permits issued from September 2024 to September 2026. After the permit, the typical finished ADU took about 12 months (363 days) from permit to final inspection (11,182 finished of 14,597 permits issued from September 2022 to September 2024; 23% had no final inspection on record by September 2026).
12 monthsfrom permit to final inspectionMiddle half: 7 months to 18 months
The two steps
The numbers behind the chart
| Step | Median | Middle half | Permits | Permits issued |
|---|---|---|---|---|
| Application to permit issued | about 4 months | 53 days to about 8 months | 15,650 | September 2024 to September 2026 |
| Permit to final inspection | about 12 months | about 7 months to about 18 months | 11,182 | September 2022 to September 2024 |
ADU builders with the most finished jobs in Los Angeles
| Rank | Contractor | Finished jobs | Contact |
|---|---|---|---|
| 1 | Baksh Construction Inc Rolling Hills Estates, licensed 18 years | Call (323) 974-2804 | |
| 2 | C S W F Construction Inc La Puente, licensed 10 years | Call (626) 825-0272 | |
| 3 | Arrow Construction Co Artesia, licensed 37 years | Call (562) 674-6171 |
See all 271 ranked ADU builders
Get quotes from up to 3 licensed ADU builders
Tell us about the job. Within one business day we email you up to 3 contractors with an active license who do this work near your ZIP code, and pass your request to them. You decide who to hire.
We got your request
Within one business day we will email you up to 3 licensed contractors who fit, and pass your request to them.
Permit wait by year issued
| Year issued | Jobs | Median | Middle half |
|---|---|---|---|
| 2022 | 1,933 | about 5 months | 68 days to about 10 months |
| 2023 | 7,115 | about 5 months | 60 days to about 10 months |
| 2024 | 7,386 | about 5 months | 55 days to about 9 months |
| 2025 | 8,103 | about 4 months | 50 days to about 8 months |
| 2026 | 5,584 | about 4 months | 55 days to about 8 months |
Why it takes this long
- 3% of permits were issued the day they were applied for, and 16% within 30 days (15,650 permits).
- 36 more permits issued in those dates carry no application date and are left out of the permit wait.
- The longer step is building and inspection: about 4 months for the permit against about 12 months from permit to final, at the median.
- 7% of finished jobs passed final inspection within 90 days of the permit.
- Of the 14,597 permits issued from September 2022 to September 2024, 3,415 (23%) had no final inspection on record by September 2026. They may still be under way, dropped or never inspected; the records do not say which. They are left out of the build time; any of them that finishes will have taken more than two years, so counting them would make the typical time longer.
Days are counted between the dates on each city permit: submitted_date, issue_date; final: status 'Permit Finaled' or a certificate, dated by cofo_date or status_date. Median and middle half: half of the jobs took longer than the median; the middle half runs from the 25th to the 75th percentile. A figure is shown only when it rests on 30 or more permits. Kinds of work are sorted by the same rules as our contractor lists. Source: City of Los Angeles, Building Permits Issued from 2020 to Present, read 2026-09-24. The same figures as data: adu.json.