How long does an EV charger permit take in Austin?

In Austin, the typical EV charger permit took 5 days from application to issue, across 1,313 permits issued from September 2024 to September 2026. After the permit, the typical finished EV charger installation took 6 days from permit to final inspection (1,475 finished of 1,562 permits issued from September 2022 to September 2024; 6% had no final inspection on record by September 2026).

5 daysfrom application to permitMiddle half: 3 days to 10 days
6 daysfrom permit to final inspectionMiddle half: 2 days to 18 days

The two steps

How long EV charger installations take in Austin, in daysApplication to permit issued: median 5 days, middle half 3 to 10 days, 1,313 permits; Permit issued to final inspection: median 6 days, middle half 2 to 18 days, 1,475 permits.Application to permit issued: 5 daysPermit issued to final inspection: 6 days07 d14 d21 d
Bars show the median; the line through each bar spans the middle half of jobs. The second step starts where the typical permit wait ends. The two steps come from different groups of permits, so they are not added up.
The numbers behind the chart
StepMedianMiddle halfPermitsPermits issued
Application to permit issued5 days3 days to 10 days1,313September 2024 to September 2026
Permit to final inspection6 days2 days to 18 days1,475September 2022 to September 2024

EV charger installers with the most jobs in Austin

RankContractorJobsContact
1Grayzer Electric LLC
1,170
Get a quote
2Charge Pro LLC
525
Get a quote
3Industrial Elect
296
Get a quote

See all 93 ranked EV charger installers

Get quotes from up to 3 EV charger installers

Tell us about the job. Within one business day we email you up to 3 contractors who do this work near your ZIP code, and pass your request to them. You decide who to hire.

When do you want to start?

We got your request

Within one business day we will email you up to 3 contractors who fit, and pass your request to them.

Permit wait by year issued

Year issuedJobsMedianMiddle half
20221405 days2 days to 8 days
20238125 days3 days to 8 days
20247936 days3 days to 10 days
20256426 days3 days to 10 days
20264874 days2 days to 6 days

Why it takes this long

  • 1% of permits were issued the day they were applied for, and 95% within 30 days (1,313 permits).
  • The longer step is building and inspection: 5 days for the permit against 6 days from permit to final, at the median.
  • 92% of finished jobs passed final inspection within 90 days of the permit.
  • Of the 1,562 permits issued from September 2022 to September 2024, 87 (6%) had no final inspection on record by September 2026. They may still be under way, dropped or never inspected; the records do not say which. They are left out of the build time; any of them that finishes will have taken more than two years, so counting them would make the typical time longer.

Days are counted between the dates on each city permit: applieddate, issue_date, completed_date. Median and middle half: half of the jobs took longer than the median; the middle half runs from the 25th to the 75th percentile. A figure is shown only when it rests on 30 or more permits. Kinds of work are sorted by the same rules as our contractor lists. Source: Austin Issued Construction Permits (data.austintexas.gov 3syk-w9eu), read 2026-09-24. The same figures as data: ev-charger.json.