How long does a pool permit take in Austin?
In Austin, the typical pool permit took 66 days from application to issue, across 1,804 permits issued from September 2024 to September 2026. After the permit, the typical finished pool or spa took about 9 months (269 days) from permit to final inspection (1,393 finished of 1,783 permits issued from September 2022 to September 2024; 22% had no final inspection on record by September 2026).
9 monthsfrom permit to final inspectionMiddle half: 5 months to 14 months
The two steps
The numbers behind the chart
| Step | Median | Middle half | Permits | Permits issued |
|---|---|---|---|---|
| Application to permit issued | 66 days | 37 days to about 5 months | 1,804 | September 2024 to September 2026 |
| Permit to final inspection | about 9 months | about 5 months to about 14 months | 1,393 | September 2022 to September 2024 |
Pool builders with the most jobs in Austin
| Rank | Contractor | Jobs | Contact |
|---|---|---|---|
| 1 | Cody Pools, Inc. | Get a quote | |
| 2 | Denali Pools LLC | Get a quote | |
| 3 | Paradisa Homes, LLC | Get a quote |
See all 294 ranked pool builders
Get quotes from up to 3 pool builders
Tell us about the job. Within one business day we email you up to 3 contractors who do this work near your ZIP code, and pass your request to them. You decide who to hire.
We got your request
Within one business day we will email you up to 3 contractors who fit, and pass your request to them.
Permit wait by year issued
| Year issued | Jobs | Median | Middle half |
|---|---|---|---|
| 2022 | 265 | about 3 months | 45 days to about 6 months |
| 2023 | 877 | 90 days | 50 days to about 7 months |
| 2024 | 827 | 78 days | 39 days to about 6 months |
| 2025 | 869 | 73 days | 43 days to about 5 months |
| 2026 | 748 | 60 days | 31 days to about 4 months |
Why it takes this long
- 0% of permits were issued the day they were applied for, and 20% within 30 days (1,804 permits).
- The longer step is building and inspection: 66 days for the permit against about 9 months from permit to final, at the median.
- 8% of finished jobs passed final inspection within 90 days of the permit.
- Of the 1,783 permits issued from September 2022 to September 2024, 390 (22%) had no final inspection on record by September 2026. They may still be under way, dropped or never inspected; the records do not say which. They are left out of the build time; any of them that finishes will have taken more than two years, so counting them would make the typical time longer.
Days are counted between the dates on each city permit: applieddate, issue_date, completed_date. Median and middle half: half of the jobs took longer than the median; the middle half runs from the 25th to the 75th percentile. A figure is shown only when it rests on 30 or more permits. Kinds of work are sorted by the same rules as our contractor lists. Source: Austin Issued Construction Permits (data.austintexas.gov 3syk-w9eu), read 2026-09-24. The same figures as data: pool.json.