How long does a remodel permit take in Austin?
In Austin, the typical remodel permit took 57 days from application to issue, across 1,546 permits issued from September 2024 to September 2026. After the permit, the typical finished remodel took about 8 months (255 days) from permit to final inspection (1,365 finished of 1,593 permits issued from September 2022 to September 2024; 14% had no final inspection on record by September 2026).
8 monthsfrom permit to final inspectionMiddle half: 5 months to 13 months
The two steps
The numbers behind the chart
| Step | Median | Middle half | Permits | Permits issued |
|---|---|---|---|---|
| Application to permit issued | 57 days | 27 days to about 4 months | 1,546 | September 2024 to September 2026 |
| Permit to final inspection | about 8 months | about 5 months to about 13 months | 1,365 | September 2022 to September 2024 |
Remodeling contractors with the most jobs in Austin
| Rank | Contractor | Jobs | Contact |
|---|---|---|---|
| 1 | Statewide Remodeling of Austin | Get a quote | |
| 2 | Together Design & Build | Get a quote | |
| 3 | Rwb Renovations LLC dba Rebath of Austin | Get a quote |
See all 379 ranked remodeling contractors
Get quotes from up to 3 remodeling contractors
Tell us about the job. Within one business day we email you up to 3 contractors who do this work near your ZIP code, and pass your request to them. You decide who to hire.
We got your request
Within one business day we will email you up to 3 contractors who fit, and pass your request to them.
Permit wait by year issued
| Year issued | Jobs | Median | Middle half |
|---|---|---|---|
| 2022 | 203 | 90 days | 42 days to about 6 months |
| 2023 | 797 | 65 days | 27 days to about 5 months |
| 2024 | 767 | 55 days | 21 days to about 4 months |
| 2025 | 773 | 59 days | 26 days to about 4 months |
| 2026 | 599 | 55 days | 29 days to about 3 months |
Why it takes this long
- 3% of permits were issued the day they were applied for, and 29% within 30 days (1,546 permits).
- The longer step is building and inspection: 57 days for the permit against about 8 months from permit to final, at the median.
- 13% of finished jobs passed final inspection within 90 days of the permit.
- Of the 1,593 permits issued from September 2022 to September 2024, 228 (14%) had no final inspection on record by September 2026. They may still be under way, dropped or never inspected; the records do not say which. They are left out of the build time; any of them that finishes will have taken more than two years, so counting them would make the typical time longer.
Days are counted between the dates on each city permit: applieddate, issue_date, completed_date. Median and middle half: half of the jobs took longer than the median; the middle half runs from the 25th to the 75th percentile. A figure is shown only when it rests on 30 or more permits. Kinds of work are sorted by the same rules as our contractor lists. Source: Austin Issued Construction Permits (data.austintexas.gov 3syk-w9eu), read 2026-09-24. The same figures as data: remodel.json.