How long does a home addition permit take in Chicago?

In Chicago, the typical home addition permit took about 3 months (103 days) from application to issue, across 960 permits issued from September 2024 to September 2026.

3 monthsfrom application to permitMiddle half: 56 days to 6 months

The two steps

How long home additions take in Chicago, in daysApplication to permit issued: median 103 days, middle half 56 to 172 days, 960 permits.Application to permit issued: about 3 months02 mo4 mo
Bars show the median; the line through each bar spans the middle half of jobs.
The numbers behind the chart
StepMedianMiddle halfPermitsPermits issued
Application to permit issuedabout 3 months56 days to about 6 months960September 2024 to September 2026

Home addition contractors with the most jobs in Chicago

RankContractorJobsContact
1Father and Sons Home Improvement II Inc
Riverside
65
Call (708) 447-7000
2Airoom, LLC
Plainfield
33
Visit website
3Leonard & Son Construction Company, Inc
Chicago
32
Get a quote

See all 186 ranked home addition contractors

Get quotes from up to 3 home addition contractors

Five quick questions. We send your request to up to 3 contractors who work near you, and email you who they are.

You decide who to hire. Your details go only to the contractors you pick. How we use your details

1. Where is the job?

We match contractors who work near it. We never ask for your street address.

2. What do you need?

Pick any that fit.

3. When do you want to start?
4. What is your rough budget?

A range is fine. It helps contractors reply with a real number.

5. Where should we send it?

Your contact details go only to who you pick here.

Sent. We have your request.

Over the next few days we email you up to 3 contractors who fit, and pass your request to them. Replies usually come within a few days.

Your job room keeps the request, your photos and every reply in one place, with an assistant that checks prices against city permits. Keep its link: it is the key to your job.

Open your job room

Permit wait by year issued

Year issuedJobsMedianMiddle half
202411382 days48 days to about 5 months
2025475about 3 months56 days to about 6 months
2026372about 4 months58 days to about 6 months

Why it takes this long

  • 0% of permits were issued the day they were applied for, and 8% within 30 days (960 permits).
  • The time to final inspection is not shown: the city's permit data has no final inspection date.

Days are counted between the dates on each city permit: application_start_date, issue_date. Median and middle half: half of the jobs took longer than the median; the middle half runs from the 25th to the 75th percentile. A figure is shown only when it rests on 30 or more permits. Kinds of work are sorted by the same rules as our contractor lists. Source: Chicago Building Permits (data.cityofchicago.org ydr8-5enu), read 2026-09-24. The same figures as data: addition.json.