How long does a remodel permit take in Chicago?
In Chicago, the typical remodel permit took 52 days from application to issue, across 1,033 permits issued from September 2024 to September 2026.
The two steps
The numbers behind the chart
| Step | Median | Middle half | Permits | Permits issued |
|---|---|---|---|---|
| Application to permit issued | 52 days | 21 days to about 3 months | 1,033 | September 2024 to September 2026 |
Remodeling contractors with the most jobs in Chicago
| Rank | Contractor | Jobs | Contact |
|---|---|---|---|
| 1 | Airoom, LLC Plainfield | Visit website | |
| 2 | Clancy & Company Contracting Western Springs | Call (815) 603-8315 | |
| 3 | Leonard & Son Construction Company, Inc Chicago | Get a quote |
See all 193 ranked remodeling contractors
Get quotes from up to 3 remodeling contractors
Five quick questions. We send your request to up to 3 contractors who work near you, and email you who they are.
Request for quotes
- Where
- Job
- Start
- Budget
- Goes to
You decide who to hire. Your details go only to the contractors you pick. How we use your details
Sent. We have your request.
Over the next few days we email you up to 3 contractors who fit, and pass your request to them. Replies usually come within a few days.
Your job room keeps the request, your photos and every reply in one place, with an assistant that checks prices against city permits. Keep its link: it is the key to your job.
Open your job roomPermit wait by year issued
| Year issued | Jobs | Median | Middle half |
|---|---|---|---|
| 2024 | 125 | 48 days | 24 days to about 3 months |
| 2025 | 535 | 52 days | 20 days to about 3 months |
| 2026 | 373 | 54 days | 22 days to about 3 months |
Why it takes this long
- 0% of permits were issued the day they were applied for, and 33% within 30 days (1,033 permits).
- The time to final inspection is not shown: the city's permit data has no final inspection date.
Days are counted between the dates on each city permit: application_start_date, issue_date. Median and middle half: half of the jobs took longer than the median; the middle half runs from the 25th to the 75th percentile. A figure is shown only when it rests on 30 or more permits. Kinds of work are sorted by the same rules as our contractor lists. Source: Chicago Building Permits (data.cityofchicago.org ydr8-5enu), read 2026-09-24. The same figures as data: remodel.json.