EV charger installation cost in Marin County (2026)

The typical EV charger installation in Marin County was valued at $3,000 on its city permit (middle half: $1,500 to $7,000), across 412 EV charger installations with city permits issued from October 2021 to October 2026.

$3,000median value on the city permit, not the price you will payMiddle half: $1,500 to $7,000412 EV charger installations, 2021 to 2026

How the values spread

Share of EV charger installations in Marin County by the value on the permitMedian $3,000. Under $5,000: 263 jobs (64%); $5,000 to $10,000: 76 jobs (18%); $10,000 to $15,000: 19 jobs (5%); $15,000 to $20,000: 9 jobs (2%); $20,000 to $25,000: 9 jobs (2%); $25,000 and over: 36 jobs (9%).64%18%5%2%2%9%Median $3,000$0$5k$10k$15k$20k$25k+
Share of EV charger installations in Marin County by the value on the permit: 412 EV charger installations, from October 2021 to October 2026. The dashed line is the median; half of all jobs fall between $1,500 and $7,000.
The numbers behind the chart
Value on the permitJobsShare
Under $5,00026364%
$5,000 to $10,0007618%
$10,000 to $15,000195%
$15,000 to $20,00092%
$20,000 to $25,00092%
$25,000 and over369%

EV charger installers with the most jobs in Marin County

RankContractorJobsContact
1Divine Electric Inc
licensed 23 years
100
Call (415) 299-0381
2Ed Electric Group Inc
licensed 3 years
22
Call (415) 497-0847
3Ernest Ongaro & Sons Inc
licensed 63 years
21
Call (707) 579-3511

See all 27 ranked EV charger installers

Get quotes from up to 3 licensed EV charger installers

Five quick questions. We send your request to up to 3 contractors who work near you, and email you who they are.

You decide who to hire. Your details go only to the contractors you pick. How we use your details

1. Where is the job?

We match contractors who work near it. We never ask for your street address.

2. What do you need?

Pick any that fit.

3. When do you want to start?
4. What is your rough budget?

A range is fine. It helps contractors reply with a real number.

5. Where should we send it?

Your contact details go only to who you pick here.

Sent. We have your request.

Over the next few days we email you up to 3 contractors who fit, and pass your request to them. Replies usually come within a few days.

Your job room keeps the request, your photos and every reply in one place, with an assistant that checks prices against city permits. Keep its link: it is the key to your job.

Open your job room

By ZIP code

The 4 ZIP codes with the most EV charger installations valued on the permit (at least 20 each).

ZIP codeJobsMedianMiddle half
94941142$3,000$1,500 to $6,400
9490372$4,300$2,000 to $7,700
9490451$2,900$1,800 to $8,000
9496027$2,500$1,500 to $3,300

By year

YearJobsMedianMiddle half
2021 (October to December)21$3,500$1,500 to $6,300
202267$4,000$1,600 to $7,700
202399$2,500$1,500 to $6,800
202472$3,400$2,000 to $7,200
202590$3,000$1,900 to $12,000
2026 (January to October)63$2,500$1,600 to $4,600

What the records show

  • Share of jobs in each budget range: under $1,500: 17% (69 of 412); $1,500 to $3,000: 33% (134 of 412); $3,000 to $6,000: 19% (79 of 412); over $6,000: 32% (130 of 412).
  • The median was $4,000 in 2022 (67 jobs) and $3,000 in 2025 (90 jobs), down 24%.
  • Across the ZIP codes above, the median ran from $2,500 in 94960 to $4,300 in 94903.

Every figure here is the job value written on the city permit, not the price paid. Permit values can be higher or lower than the final price, so get more than one quote. Values under $1,000 are placeholders and are left out. Median and middle half: half of the jobs were valued above the median; the middle half runs from the 25th to the 75th percentile. Source: Marin County building permits (unincorporated areas; city permits not included), from October 2021 to October 2026. Data updated October 6, 2026. The same figures as data: ev-charger.json.