How long does a home addition permit take in New York?
In New York, the typical home addition permit took about 6 months (193 days) from application to issue, across 347 permits issued from September 2024 to September 2026. After the permit, the typical finished home addition took about 15 months (444 days) from permit to final inspection (134 finished of 352 permits issued from September 2022 to September 2024; 62% had no final inspection on record by September 2026).
15 monthsfrom permit to final inspectionMiddle half: 8 months to 22 months
The two steps
The numbers behind the chart
| Step | Median | Middle half | Permits | Permits issued |
|---|---|---|---|---|
| Application to permit issued | about 6 months | about 3 months to about 13 months | 347 | September 2024 to September 2026 |
| Permit to final inspection | about 15 months | about 8 months to about 22 months | 134 | September 2022 to September 2024 |
Home addition contractors with the most jobs in New York
| Rank | Contractor | Jobs | Contact |
|---|---|---|---|
| 1 | Mdg Design & Constr LLC Woodbury, license 31838 | Visit website | |
| 2 | Moken Home Improvement Baldwin, license 616733 | Call (718) 371-8882 | |
| 3 | Custombuilt Homes Inc Bellerose, license 36215 | Call (718) 470-1171 |
See all 37 ranked home addition contractors
Get quotes from up to 3 licensed home addition contractors
Five quick questions. We send your request to up to 3 contractors who work near you, and email you who they are.
Request for quotes
- Where
- Job
- Start
- Budget
- Goes to
You decide who to hire. Your details go only to the contractors you pick. How we use your details
Sent. We have your request.
Over the next few days we email you up to 3 contractors who fit, and pass your request to them. Replies usually come within a few days.
Your job room keeps the request, your photos and every reply in one place, with an assistant that checks prices against city permits. Keep its link: it is the key to your job.
Open your job roomPermit wait by year issued
| Year issued | Jobs | Median | Middle half |
|---|---|---|---|
| 2022 | 45 | about 6 months | 85 days to about 9 months |
| 2023 | 181 | about 6 months | 89 days to about 9 months |
| 2024 | 173 | about 6 months | about 4 months to about 14 months |
| 2025 | 169 | about 5 months | about 3 months to about 10 months |
| 2026 | 131 | about 9 months | about 4 months to about 15 months |
Why it takes this long
- 0% of permits were issued the day they were applied for, and 5% within 30 days (347 permits).
- The longer step is building and inspection: about 6 months for the permit against about 15 months from permit to final, at the median.
- 9% of finished jobs passed final inspection within 90 days of the permit.
- Of the 352 permits issued from September 2022 to September 2024, 218 (62%) had no final inspection on record by September 2026. They may still be under way, dropped or never inspected; the records do not say which. They are left out of the build time; any of them that finishes will have taken more than two years, so counting them would make the typical time longer.
Days are counted between the dates on each city permit: filing_date, issued_date, signoff_date. Median and middle half: half of the jobs took longer than the median; the middle half runs from the 25th to the 75th percentile. A figure is shown only when it rests on 30 or more permits. Kinds of work are sorted by the same rules as our contractor lists. Source: NYC DOB NOW: Build, Approved Permits (rbx6-tga4) joined to Job Application Filings (w9ak-ipjd), read 2026-09-24. The same figures as data: addition.json.