How long does a heat pump permit take in New York?

In New York, the typical heat pump permit took 57 days from application to issue, across 1,155 permits issued from September 2024 to September 2026. After the permit, the typical finished heat pump installation took about 6 months (190 days) from permit to final inspection (604 finished of 768 permits issued from September 2022 to September 2024; 21% had no final inspection on record by September 2026).

57 daysfrom application to permitMiddle half: 18 days to 5 months
6 monthsfrom permit to final inspectionMiddle half: 70 days to 13 months

The two steps

How long heat pump installations take in New York, in daysApplication to permit issued: median 57 days, middle half 18 to 147 days, 1,155 permits; Permit issued to final inspection: median 190 days, middle half 70 to 400 days, 604 permits.Application to permit issued: 57 daysPermit issued to final inspection: about 6 months06 mo12 mo
Bars show the median; the line through each bar spans the middle half of jobs. The second step starts where the typical permit wait ends. The two steps come from different groups of permits, so they are not added up.
The numbers behind the chart
StepMedianMiddle halfPermitsPermits issued
Application to permit issued57 days18 days to about 5 months1,155September 2024 to September 2026
Permit to final inspectionabout 6 months70 days to about 13 months604September 2022 to September 2024

Heat pump installers with the most jobs in New York

RankContractorJobsContact
1Dvm Industries LLC
Poughkeepsie, license 627423
88
Call (917) 659-0088
2The Sci Construction
Long Island.City, license 616630
51
Call (646) 789-4564
3Ice Age Mechanical Corp
Brooklyn, license 614762
27
Call (718) 344-5095

See all 118 ranked heat pump installers

Get quotes from up to 3 licensed heat pump installers

Tell us about the job. Within one business day we email you up to 3 contractors with an active license who do this work near your ZIP code, and pass your request to them. You decide who to hire.

When do you want to start?

We got your request

Within one business day we will email you up to 3 licensed contractors who fit, and pass your request to them.

Permit wait by year issued

Year issuedJobsMedianMiddle half
20229140 days16 days to about 4 months
202337743 days13 days to about 6 months
202443541 days13 days to about 5 months
202548050 days17 days to about 6 months
202654062 days18 days to about 5 months

Why it takes this long

  • 0% of permits were issued the day they were applied for, and 35% within 30 days (1,155 permits).
  • The longer step is building and inspection: 57 days for the permit against about 6 months from permit to final, at the median.
  • 30% of finished jobs passed final inspection within 90 days of the permit.
  • Of the 768 permits issued from September 2022 to September 2024, 164 (21%) had no final inspection on record by September 2026. They may still be under way, dropped or never inspected; the records do not say which. They are left out of the build time; any of them that finishes will have taken more than two years, so counting them would make the typical time longer.

Days are counted between the dates on each city permit: filing_date, issued_date, signoff_date. Median and middle half: half of the jobs took longer than the median; the middle half runs from the 25th to the 75th percentile. A figure is shown only when it rests on 30 or more permits. Kinds of work are sorted by the same rules as our contractor lists. Source: NYC DOB NOW: Build, Approved Permits (rbx6-tga4) joined to Job Application Filings (w9ak-ipjd), read 2026-09-24. The same figures as data: heat-pump.json.