How long does a heat pump permit take in New York?
In New York, the typical heat pump permit took 57 days from application to issue, across 1,155 permits issued from September 2024 to September 2026. After the permit, the typical finished heat pump installation took about 6 months (190 days) from permit to final inspection (604 finished of 768 permits issued from September 2022 to September 2024; 21% had no final inspection on record by September 2026).
6 monthsfrom permit to final inspectionMiddle half: 70 days to 13 months
The two steps
The numbers behind the chart
| Step | Median | Middle half | Permits | Permits issued |
|---|---|---|---|---|
| Application to permit issued | 57 days | 18 days to about 5 months | 1,155 | September 2024 to September 2026 |
| Permit to final inspection | about 6 months | 70 days to about 13 months | 604 | September 2022 to September 2024 |
Heat pump installers with the most jobs in New York
| Rank | Contractor | Jobs | Contact |
|---|---|---|---|
| 1 | Dvm Industries LLC Poughkeepsie, license 627423 | Call (917) 659-0088 | |
| 2 | The Sci Construction Long Island.City, license 616630 | Call (646) 789-4564 | |
| 3 | Ice Age Mechanical Corp Brooklyn, license 614762 | Call (718) 344-5095 |
See all 118 ranked heat pump installers
Get quotes from up to 3 licensed heat pump installers
Tell us about the job. Within one business day we email you up to 3 contractors with an active license who do this work near your ZIP code, and pass your request to them. You decide who to hire.
We got your request
Within one business day we will email you up to 3 licensed contractors who fit, and pass your request to them.
Permit wait by year issued
| Year issued | Jobs | Median | Middle half |
|---|---|---|---|
| 2022 | 91 | 40 days | 16 days to about 4 months |
| 2023 | 377 | 43 days | 13 days to about 6 months |
| 2024 | 435 | 41 days | 13 days to about 5 months |
| 2025 | 480 | 50 days | 17 days to about 6 months |
| 2026 | 540 | 62 days | 18 days to about 5 months |
Why it takes this long
- 0% of permits were issued the day they were applied for, and 35% within 30 days (1,155 permits).
- The longer step is building and inspection: 57 days for the permit against about 6 months from permit to final, at the median.
- 30% of finished jobs passed final inspection within 90 days of the permit.
- Of the 768 permits issued from September 2022 to September 2024, 164 (21%) had no final inspection on record by September 2026. They may still be under way, dropped or never inspected; the records do not say which. They are left out of the build time; any of them that finishes will have taken more than two years, so counting them would make the typical time longer.
Days are counted between the dates on each city permit: filing_date, issued_date, signoff_date. Median and middle half: half of the jobs took longer than the median; the middle half runs from the 25th to the 75th percentile. A figure is shown only when it rests on 30 or more permits. Kinds of work are sorted by the same rules as our contractor lists. Source: NYC DOB NOW: Build, Approved Permits (rbx6-tga4) joined to Job Application Filings (w9ak-ipjd), read 2026-09-24. The same figures as data: heat-pump.json.