How long does a solar permit take in New York?
In New York, the typical solar permit took 7 days from application to issue, across 11,268 permits issued from September 2024 to September 2026. After the permit, the typical finished solar installation took about 4 months (122 days) from permit to final inspection (4,228 finished of 4,853 permits issued from October 2022 to September 2024; 13% had no final inspection on record by September 2026).
4 monthsfrom permit to final inspectionMiddle half: 68 days to 7 months
The two steps
The numbers behind the chart
| Step | Median | Middle half | Permits | Permits issued |
|---|---|---|---|---|
| Application to permit issued | 7 days | 4 days to 15 days | 11,268 | September 2024 to September 2026 |
| Permit to final inspection | about 4 months | 68 days to about 7 months | 4,228 | October 2022 to September 2024 |
Solar installers with the most jobs in New York
| Rank | Contractor | Jobs | Contact |
|---|---|---|---|
| 1 | Sunrun Installation Svc San Luis Obispo, license 613329 | Call (805) 540-7643 | |
| 2 | Nyss LLC Hicksville, license 622219 | Call (516) 418-2131 | |
| 3 | Kamtech Restoration Corp Inwood, license 616224 | Call (718) 915-8360 |
See all 61 ranked solar installers
Get quotes from up to 3 licensed solar installers
Tell us about the job. Within one business day we email you up to 3 contractors with an active license who do this work near your ZIP code, and pass your request to them. You decide who to hire.
We got your request
Within one business day we will email you up to 3 licensed contractors who fit, and pass your request to them.
Permit wait by year issued
| Year issued | Jobs | Median | Middle half |
|---|---|---|---|
| 2023 | 235 | 7 days | 5 days to 12 days |
| 2024 | 6,657 | 8 days | 5 days to 19 days |
| 2025 | 6,760 | 7 days | 4 days to 15 days |
| 2026 | 2,467 | 7 days | 4 days to 14 days |
Why it takes this long
- 1% of permits were issued the day they were applied for, and 88% within 30 days (11,268 permits).
- The longer step is building and inspection: 7 days for the permit against about 4 months from permit to final, at the median.
- 38% of finished jobs passed final inspection within 90 days of the permit.
- Of the 4,853 permits issued from October 2022 to September 2024, 625 (13%) had no final inspection on record by September 2026. They may still be under way, dropped or never inspected; the records do not say which. They are left out of the build time; any of them that finishes will have taken more than two years, so counting them would make the typical time longer.
Days are counted between the dates on each city permit: filing_date, issued_date, signoff_date. Median and middle half: half of the jobs took longer than the median; the middle half runs from the 25th to the 75th percentile. A figure is shown only when it rests on 30 or more permits. Kinds of work are sorted by the same rules as our contractor lists. Source: NYC DOB NOW: Build, Approved Permits (rbx6-tga4) joined to Job Application Filings (w9ak-ipjd), read 2026-09-24. The same figures as data: solar.json.