How long does a home addition take in Philadelphia?
In Philadelphia, the typical finished home addition took about 12 months (376 days) from permit to final inspection (504 finished of 583 permits issued from September 2022 to September 2024; 14% had no final inspection on record by September 2026).
The two steps
The numbers behind the chart
| Step | Median | Middle half | Permits | Permits issued |
|---|---|---|---|---|
| Permit to final inspection | about 12 months | about 8 months to about 20 months | 504 | September 2022 to September 2024 |
Home addition contractors with the most jobs in Philadelphia
| Rank | Contractor | Jobs | Contact |
|---|---|---|---|
| 1 | Citylife Collective LLC | Get a quote | |
| 2 | John Hines | Get a quote | |
| 3 | Lapstone LLC | Visit website |
See all 104 ranked home addition contractors
Get quotes from up to 3 licensed home addition contractors
Five quick questions. We send your request to up to 3 contractors who work near you, and email you who they are.
Request for quotes
- Where
- Job
- Start
- Budget
- Goes to
You decide who to hire. Your details go only to the contractors you pick. How we use your details
Sent. We have your request.
Over the next few days we email you up to 3 contractors who fit, and pass your request to them. Replies usually come within a few days.
Your job room keeps the request, your photos and every reply in one place, with an assistant that checks prices against city permits. Keep its link: it is the key to your job.
Open your job roomWhy it takes this long
- 5% of finished jobs passed final inspection within 90 days of the permit.
- Of the 583 permits issued from September 2022 to September 2024, 79 (14%) had no final inspection on record by September 2026. They may still be under way, dropped or never inspected; the records do not say which. They are left out of the build time; any of them that finishes will have taken more than two years, so counting them would make the typical time longer.
- The permit wait is not shown: the city's permit data has no application date.
Days are counted between the dates on each city permit: permitissuedate, permitcompleteddate. Median and middle half: half of the jobs took longer than the median; the middle half runs from the 25th to the 75th percentile. A figure is shown only when it rests on 30 or more permits. Kinds of work are sorted by the same rules as our contractor lists. Source: Philadelphia Licenses and Inspections, Building and Zoning Permits (phl.carto.com permits), read 2026-09-24. The same figures as data: addition.json.