How long does a panel upgrade take in Philadelphia?

In Philadelphia, the typical finished panel upgrade took about 3 months (97 days) from permit to final inspection (3,547 finished of 3,707 permits issued from September 2022 to September 2024; 4% had no final inspection on record by September 2026).

3 monthsfrom permit to final inspectionMiddle half: 27 days to 7 months

The two steps

How long panel upgrades take in Philadelphia, in daysPermit issued to final inspection: median 97 days, middle half 27 to 208 days, 3,547 permits.Permit issued to final inspection: about 3 months02 mo4 mo6 mo
Bars show the median; the line through each bar spans the middle half of jobs.
The numbers behind the chart
StepMedianMiddle halfPermitsPermits issued
Permit to final inspectionabout 3 months27 days to about 7 months3,547September 2022 to September 2024

Panel upgrade electricians with the most jobs in Philadelphia

RankContractorJobsContact
1Generation 3 Electric Inc
605
Get a quote
2Tyree Strickland Electric, LLC
564
Get a quote
3Anthony L Davis Jr
295
Get a quote

See all 126 ranked panel upgrade electricians

Get quotes from up to 3 licensed panel upgrade electricians

Five quick questions. We send your request to up to 3 contractors who work near you, and email you who they are.

You decide who to hire. Your details go only to the contractors you pick. How we use your details

1. Where is the job?

We match contractors who work near it. We never ask for your street address.

2. What do you need?

Pick any that fit.

3. When do you want to start?
4. What is your rough budget?

A range is fine. It helps contractors reply with a real number.

5. Where should we send it?

Your contact details go only to who you pick here.

Sent. We have your request.

Over the next few days we email you up to 3 contractors who fit, and pass your request to them. Replies usually come within a few days.

Your job room keeps the request, your photos and every reply in one place, with an assistant that checks prices against city permits. Keep its link: it is the key to your job.

Open your job room

Why it takes this long

  • 48% of finished jobs passed final inspection within 90 days of the permit.
  • Of the 3,707 permits issued from September 2022 to September 2024, 160 (4%) had no final inspection on record by September 2026. They may still be under way, dropped or never inspected; the records do not say which. They are left out of the build time; any of them that finishes will have taken more than two years, so counting them would make the typical time longer.
  • The permit wait is not shown: the city's permit data has no application date.

Days are counted between the dates on each city permit: permitissuedate, permitcompleteddate. Median and middle half: half of the jobs took longer than the median; the middle half runs from the 25th to the 75th percentile. A figure is shown only when it rests on 30 or more permits. Kinds of work are sorted by the same rules as our contractor lists. Source: Philadelphia Licenses and Inspections, Building and Zoning Permits (phl.carto.com permits), read 2026-09-24. The same figures as data: electrical-panel.json.