How long does a heat pump installation take in Philadelphia?

In Philadelphia, the typical finished heat pump installation took about 8 months (229 days) from permit to final inspection (538 finished of 564 permits issued from September 2022 to September 2024; 5% had no final inspection on record by September 2026).

8 monthsfrom permit to final inspectionMiddle half: 4 months to 12 months

The two steps

How long heat pump installations take in Philadelphia, in daysPermit issued to final inspection: median 229 days, middle half 136 to 380 days, 538 permits.Permit issued to final inspection: about 8 months03 mo6 mo9 mo12 mo
Bars show the median; the line through each bar spans the middle half of jobs.
The numbers behind the chart
StepMedianMiddle halfPermitsPermits issued
Permit to final inspectionabout 8 monthsabout 4 months to about 12 months538September 2022 to September 2024

Heat pump installers with the most jobs in Philadelphia

RankContractorJobsContact
1Sanks Mechanical
56
Get a quote
2Angel Heating & Cooling Inc
38
Get a quote
3A & G Heating and Cooling LLC
36
Get a quote

See all 82 ranked heat pump installers

Get quotes from up to 3 licensed heat pump installers

Tell us about the job. Within one business day we email you up to 3 contractors with an active license who do this work near your ZIP code, and pass your request to them. You decide who to hire.

When do you want to start?

We got your request

Within one business day we will email you up to 3 licensed contractors who fit, and pass your request to them.

Why it takes this long

  • 14% of finished jobs passed final inspection within 90 days of the permit.
  • Of the 564 permits issued from September 2022 to September 2024, 26 (5%) had no final inspection on record by September 2026. They may still be under way, dropped or never inspected; the records do not say which. They are left out of the build time; any of them that finishes will have taken more than two years, so counting them would make the typical time longer.
  • The permit wait is not shown: the city's permit data has no application date.

Days are counted between the dates on each city permit: permitissuedate, permitcompleteddate. Median and middle half: half of the jobs took longer than the median; the middle half runs from the 25th to the 75th percentile. A figure is shown only when it rests on 30 or more permits. Kinds of work are sorted by the same rules as our contractor lists. Source: Philadelphia Licenses and Inspections, Building and Zoning Permits (phl.carto.com permits), read 2026-09-24. The same figures as data: heat-pump.json.