How long does a pool permit take in Los Angeles?

In Los Angeles, the typical pool permit took 28 days from application to issue, across 4,464 permits issued from September 2024 to September 2026. After the permit, the typical finished pool or spa took about 8 months (253 days) from permit to final inspection (3,690 finished of 5,071 permits issued from September 2022 to September 2024; 27% had no final inspection on record by September 2026).

28 daysfrom application to permitMiddle half: same day to 3 months
8 monthsfrom permit to final inspectionMiddle half: 4 months to 15 months

The two steps

How long pools and spas take in Los Angeles, in daysApplication to permit issued: median 28 days, middle half 0 to 95 days, 4,464 permits; Permit issued to final inspection: median 253 days, middle half 117 to 453 days, 3,690 permits.Application to permit issued: 28 daysPermit issued to final inspection: about 8 months06 mo12 mo
Bars show the median; the line through each bar spans the middle half of jobs. The second step starts where the typical permit wait ends. The two steps come from different groups of permits, so they are not added up.
The numbers behind the chart
StepMedianMiddle halfPermitsPermits issued
Application to permit issued28 dayssame day to about 3 months4,464September 2024 to September 2026
Permit to final inspectionabout 8 monthsabout 4 months to about 15 months3,690September 2022 to September 2024

Pool builders with the most finished jobs in Los Angeles

RankContractorFinished jobsContact
1Agam Pool and Spa Inc
Sherman Oaks, licensed 12 years
70
Visit website
2Coastal Aquatic Creations
Los Angeles, licensed 32 years
70
Visit website
3Avanti Pools Inc
Van Nuys, licensed 27 years
55
Visit website

See all 181 ranked pool builders

Get quotes from up to 3 licensed pool builders

Five quick questions. We send your request to up to 3 contractors who work near you, and email you who they are.

You decide who to hire. Your details go only to the contractors you pick. How we use your details

1. Where is the job?

We match contractors who work near it. We never ask for your street address.

2. What do you need?

Pick any that fit.

3. When do you want to start?
4. What is your rough budget?

A range is fine. It helps contractors reply with a real number.

5. Where should we send it?

Your contact details go only to who you pick here.

Sent. We have your request.

Over the next few days we email you up to 3 contractors who fit, and pass your request to them. Replies usually come within a few days.

Your job room keeps the request, your photos and every reply in one place, with an assistant that checks prices against city permits. Keep its link: it is the key to your job.

Open your job room

Permit wait by year issued

Year issuedJobsMedianMiddle half
202272938 days3 days to about 4 months
20232,43129 dayssame day to about 4 months
20242,33022 dayssame day to about 3 months
20252,17326 dayssame day to about 3 months
20261,70932 days1 day to about 3 months

Why it takes this long

  • 26% of permits were issued the day they were applied for, and 51% within 30 days (4,464 permits).
  • 112 more permits issued in those dates carry no application date and are left out of the permit wait.
  • The longer step is building and inspection: 28 days for the permit against about 8 months from permit to final, at the median.
  • 20% of finished jobs passed final inspection within 90 days of the permit.
  • Of the 5,071 permits issued from September 2022 to September 2024, 1,381 (27%) had no final inspection on record by September 2026. They may still be under way, dropped or never inspected; the records do not say which. They are left out of the build time; any of them that finishes will have taken more than two years, so counting them would make the typical time longer.

Days are counted between the dates on each city permit: submitted_date, issue_date; final: status 'Permit Finaled' or a certificate, dated by cofo_date or status_date. Median and middle half: half of the jobs took longer than the median; the middle half runs from the 25th to the 75th percentile. A figure is shown only when it rests on 30 or more permits. Kinds of work are sorted by the same rules as our contractor lists. Source: City of Los Angeles, Building Permits Issued from 2020 to Present, read 2026-09-24. The same figures as data: pool.json.