How long does a pool permit take in Los Angeles?
In Los Angeles, the typical pool permit took 28 days from application to issue, across 4,464 permits issued from September 2024 to September 2026. After the permit, the typical finished pool or spa took about 8 months (253 days) from permit to final inspection (3,690 finished of 5,071 permits issued from September 2022 to September 2024; 27% had no final inspection on record by September 2026).
8 monthsfrom permit to final inspectionMiddle half: 4 months to 15 months
The two steps
The numbers behind the chart
| Step | Median | Middle half | Permits | Permits issued |
|---|---|---|---|---|
| Application to permit issued | 28 days | same day to about 3 months | 4,464 | September 2024 to September 2026 |
| Permit to final inspection | about 8 months | about 4 months to about 15 months | 3,690 | September 2022 to September 2024 |
Pool builders with the most finished jobs in Los Angeles
| Rank | Contractor | Finished jobs | Contact |
|---|---|---|---|
| 1 | Coastal Aquatic Creations Los Angeles, licensed 32 years | Visit website | |
| 2 | Agam Pool and Spa Inc Sherman Oaks, licensed 12 years | Call (818) 915-1919 | |
| 3 | Avanti Pools Inc Van Nuys, licensed 27 years | Call (818) 501-3759 |
See all 182 ranked pool builders
Get quotes from up to 3 licensed pool builders
Tell us about the job. Within one business day we email you up to 3 contractors with an active license who do this work near your ZIP code, and pass your request to them. You decide who to hire.
We got your request
Within one business day we will email you up to 3 licensed contractors who fit, and pass your request to them.
Permit wait by year issued
| Year issued | Jobs | Median | Middle half |
|---|---|---|---|
| 2022 | 729 | 38 days | 3 days to about 4 months |
| 2023 | 2,431 | 29 days | same day to about 4 months |
| 2024 | 2,330 | 22 days | same day to about 3 months |
| 2025 | 2,173 | 26 days | same day to about 3 months |
| 2026 | 1,709 | 32 days | 1 day to about 3 months |
Why it takes this long
- 26% of permits were issued the day they were applied for, and 51% within 30 days (4,464 permits).
- 112 more permits issued in those dates carry no application date and are left out of the permit wait.
- The longer step is building and inspection: 28 days for the permit against about 8 months from permit to final, at the median.
- 20% of finished jobs passed final inspection within 90 days of the permit.
- Of the 5,071 permits issued from September 2022 to September 2024, 1,381 (27%) had no final inspection on record by September 2026. They may still be under way, dropped or never inspected; the records do not say which. They are left out of the build time; any of them that finishes will have taken more than two years, so counting them would make the typical time longer.
Days are counted between the dates on each city permit: submitted_date, issue_date; final: status 'Permit Finaled' or a certificate, dated by cofo_date or status_date. Median and middle half: half of the jobs took longer than the median; the middle half runs from the 25th to the 75th percentile. A figure is shown only when it rests on 30 or more permits. Kinds of work are sorted by the same rules as our contractor lists. Source: City of Los Angeles, Building Permits Issued from 2020 to Present, read 2026-09-24. The same figures as data: pool.json.