How long does a remodel take in Los Angeles?

In Los Angeles, the typical finished remodel took about 6 months (189 days) from permit to final inspection (11,194 finished of 15,381 permits issued from September 2022 to September 2024; 27% had no final inspection on record by September 2026).

6 monthsfrom permit to final inspectionMiddle half: 3 months to 12 months

The two steps

How long remodels take in Los Angeles, in daysPermit issued to final inspection: median 189 days, middle half 92 to 367 days, 11,194 permits.Permit issued to final inspection: about 6 months03 mo6 mo9 mo12 mo
Bars show the median; the line through each bar spans the middle half of jobs.
The numbers behind the chart
StepMedianMiddle halfPermitsPermits issued
Permit to final inspectionabout 6 monthsabout 3 months to about 12 months11,194September 2022 to September 2024

Remodeling contractors with the most jobs in Los Angeles

RankContractorJobsContact
1Douglas Emmett Builders
Santa Monica, licensed 34 years
242
Call (310) 255-7800
2Preferred Home Builders Inc
Canoga Park, licensed 26 years
188
Visit website
3One Week Bath Inc
licensed 26 years
132
Visit website

See all 1,657 ranked remodeling contractors

Get quotes from up to 3 licensed remodeling contractors

Five quick questions. We send your request to up to 3 contractors who work near you, and email you who they are.

You decide who to hire. Your details go only to the contractors you pick. How we use your details

1. Where is the job?

We match contractors who work near it. We never ask for your street address.

2. What do you need?

Pick any that fit.

3. When do you want to start?
4. What is your rough budget?

A range is fine. It helps contractors reply with a real number.

5. Where should we send it?

Your contact details go only to who you pick here.

Sent. We have your request.

Over the next few days we email you up to 3 contractors who fit, and pass your request to them. Replies usually come within a few days.

Your job room keeps the request, your photos and every reply in one place, with an assistant that checks prices against city permits. Keep its link: it is the key to your job.

Open your job room

Why it takes this long

  • 24% of finished jobs passed final inspection within 90 days of the permit.
  • Of the 15,381 permits issued from September 2022 to September 2024, 4,187 (27%) had no final inspection on record by September 2026. They may still be under way, dropped or never inspected; the records do not say which. They are left out of the build time; any of them that finishes will have taken more than two years, so counting them would make the typical time longer.
  • The permit wait is not shown: 52% of 15,951 permits carry no application date, so the rest would not show the typical wait.

Days are counted between the dates on each city permit: submitted_date, issue_date; final: status 'Permit Finaled' or a certificate, dated by cofo_date or status_date. Median and middle half: half of the jobs took longer than the median; the middle half runs from the 25th to the 75th percentile. A figure is shown only when it rests on 30 or more permits. Kinds of work are sorted by the same rules as our contractor lists. Source: City of Los Angeles, Building Permits Issued from 2020 to Present, read 2026-09-24. The same figures as data: remodel.json.