How long does a roof replacement take in Los Angeles?
In Los Angeles, the typical finished roofing job took 26 days from permit to final inspection (20,043 finished of 25,665 permits issued from September 2022 to September 2024; 22% had no final inspection on record by September 2026).
The two steps
The numbers behind the chart
| Step | Median | Middle half | Permits | Permits issued |
|---|---|---|---|---|
| Permit to final inspection | 26 days | 14 days to 56 days | 20,043 | September 2022 to September 2024 |
Roofing contractors with the most jobs in Los Angeles
| Rank | Contractor | Jobs | Contact |
|---|---|---|---|
| 1 | Roof Repair Specialist Burbank, licensed 11 years | Call (626) 869-7663 | |
| 2 | Smart Roofing Inc Valley Village, licensed 6 years | Call (818) 301-9755 | |
| 3 | Trujano Roofing Los Angeles, licensed 7 years | Call (323) 519-1548 |
See all 807 ranked roofing contractors
Get quotes from up to 3 licensed roofing contractors
Tell us about the job. Within one business day we email you up to 3 contractors with an active license who do this work near your ZIP code, and pass your request to them. You decide who to hire.
We got your request
Within one business day we will email you up to 3 licensed contractors who fit, and pass your request to them.
Why it takes this long
- 84% of finished jobs passed final inspection within 90 days of the permit.
- Of the 25,665 permits issued from September 2022 to September 2024, 5,622 (22%) had no final inspection on record by September 2026. They may still be under way, dropped or never inspected; the records do not say which. They are left out of the build time; any of them that finishes will have taken more than two years, so counting them would make the typical time longer.
- The permit wait is not shown: 100% of 24,330 permits carry no application date, so the rest would not show the typical wait.
Days are counted between the dates on each city permit: submitted_date, issue_date; final: status 'Permit Finaled' or a certificate, dated by cofo_date or status_date. Median and middle half: half of the jobs took longer than the median; the middle half runs from the 25th to the 75th percentile. A figure is shown only when it rests on 30 or more permits. Kinds of work are sorted by the same rules as our contractor lists. Source: City of Los Angeles, Building Permits Issued from 2020 to Present, read 2026-09-24. The same figures as data: roofing.json.