How long does a home addition permit take in San Francisco?

In San Francisco, the typical home addition permit took about 5 months (160 days) from application to issue, across 428 permits issued from September 2024 to September 2026. After the permit, the typical finished home addition took about 16 months (475 days) from permit to final inspection (213 finished of 397 permits issued from September 2022 to September 2024; 46% had no final inspection on record by September 2026).

5 monthsfrom application to permitMiddle half: 52 days to 15 months
16 monthsfrom permit to final inspectionMiddle half: 8 months to 2 years

The two steps

How long home additions take in San Francisco, in daysApplication to permit issued: median 160 days, middle half 52 to 445 days, 428 permits; Permit issued to final inspection: median 475 days, middle half 258 to 725 days, 213 permits.Application to permit issued: about 5 monthsPermit issued to final inspection: about 16 months06 mo12 mo18 mo24 mo
Bars show the median; the line through each bar spans the middle half of jobs. The second step starts where the typical permit wait ends. The two steps come from different groups of permits, so they are not added up.
The numbers behind the chart
StepMedianMiddle halfPermitsPermits issued
Application to permit issuedabout 5 months52 days to about 15 months428September 2024 to September 2026
Permit to final inspectionabout 16 monthsabout 8 months to about 2 years213September 2022 to September 2024

Home addition contractors with the most jobs in San Francisco

RankContractorJobsContact
1Mission Home Remodeling Inc
San Francisco, licensed 5 years
8
Visit website
2Saturn Construction Co
San Francisco, licensed 21 years
7
Visit website
3C H Burnham Inc
San Francisco, licensed 15 years
6
Call (415) 407-4036

See all 45 ranked home addition contractors

Get quotes from up to 3 licensed home addition contractors

Tell us about the job. Within one business day we email you up to 3 contractors with an active license who do this work near your ZIP code, and pass your request to them. You decide who to hire.

When do you want to start?

We got your request

Within one business day we will email you up to 3 licensed contractors who fit, and pass your request to them.

Permit wait by year issued

Year issuedJobsMedianMiddle half
202237about 17 monthsabout 11 months to about 21 months
2023206about 15 monthsabout 6 months to about 2 years
2024198about 13 monthsabout 3 months to about 2.1 years
2025223about 4 months46 days to about 18 months
2026160about 6 months70 days to about 10 months

Why it takes this long

  • 4% of permits were issued the day they were applied for, and 19% within 30 days (428 permits).
  • 3 more permits issued in those dates carry no application date and are left out of the permit wait.
  • The longer step is building and inspection: about 5 months for the permit against about 16 months from permit to final, at the median.
  • 6% of finished jobs passed final inspection within 90 days of the permit.
  • Of the 397 permits issued from September 2022 to September 2024, 184 (46%) had no final inspection on record by September 2026. They may still be under way, dropped or never inspected; the records do not say which. They are left out of the build time; any of them that finishes will have taken more than two years, so counting them would make the typical time longer.

Days are counted between the dates on each city permit: filed_date, issued_date, completed_date. Median and middle half: half of the jobs took longer than the median; the middle half runs from the 25th to the 75th percentile. A figure is shown only when it rests on 30 or more permits. Kinds of work are sorted by the same rules as our contractor lists. Source: San Francisco Building, Electrical and Plumbing Permits (data.sf.gov i98e-djp9, ftty-kx6y, a6aw-rudh), read 2026-09-24. The same figures as data: addition.json.