How long does a home addition permit take in San Francisco?
In San Francisco, the typical home addition permit took about 5 months (160 days) from application to issue, across 428 permits issued from September 2024 to September 2026. After the permit, the typical finished home addition took about 16 months (475 days) from permit to final inspection (213 finished of 397 permits issued from September 2022 to September 2024; 46% had no final inspection on record by September 2026).
16 monthsfrom permit to final inspectionMiddle half: 8 months to 2 years
The two steps
The numbers behind the chart
| Step | Median | Middle half | Permits | Permits issued |
|---|---|---|---|---|
| Application to permit issued | about 5 months | 52 days to about 15 months | 428 | September 2024 to September 2026 |
| Permit to final inspection | about 16 months | about 8 months to about 2 years | 213 | September 2022 to September 2024 |
Home addition contractors with the most jobs in San Francisco
| Rank | Contractor | Jobs | Contact |
|---|---|---|---|
| 1 | Mission Home Remodeling Inc San Francisco, licensed 5 years | Visit website | |
| 2 | Saturn Construction Co San Francisco, licensed 21 years | Visit website | |
| 3 | C H Burnham Inc San Francisco, licensed 15 years | Call (415) 407-4036 |
See all 45 ranked home addition contractors
Get quotes from up to 3 licensed home addition contractors
Tell us about the job. Within one business day we email you up to 3 contractors with an active license who do this work near your ZIP code, and pass your request to them. You decide who to hire.
We got your request
Within one business day we will email you up to 3 licensed contractors who fit, and pass your request to them.
Permit wait by year issued
| Year issued | Jobs | Median | Middle half |
|---|---|---|---|
| 2022 | 37 | about 17 months | about 11 months to about 21 months |
| 2023 | 206 | about 15 months | about 6 months to about 2 years |
| 2024 | 198 | about 13 months | about 3 months to about 2.1 years |
| 2025 | 223 | about 4 months | 46 days to about 18 months |
| 2026 | 160 | about 6 months | 70 days to about 10 months |
Why it takes this long
- 4% of permits were issued the day they were applied for, and 19% within 30 days (428 permits).
- 3 more permits issued in those dates carry no application date and are left out of the permit wait.
- The longer step is building and inspection: about 5 months for the permit against about 16 months from permit to final, at the median.
- 6% of finished jobs passed final inspection within 90 days of the permit.
- Of the 397 permits issued from September 2022 to September 2024, 184 (46%) had no final inspection on record by September 2026. They may still be under way, dropped or never inspected; the records do not say which. They are left out of the build time; any of them that finishes will have taken more than two years, so counting them would make the typical time longer.
Days are counted between the dates on each city permit: filed_date, issued_date, completed_date. Median and middle half: half of the jobs took longer than the median; the middle half runs from the 25th to the 75th percentile. A figure is shown only when it rests on 30 or more permits. Kinds of work are sorted by the same rules as our contractor lists. Source: San Francisco Building, Electrical and Plumbing Permits (data.sf.gov i98e-djp9, ftty-kx6y, a6aw-rudh), read 2026-09-24. The same figures as data: addition.json.