How long does a remodel permit take in San Francisco?

In San Francisco, the typical remodel permit was issued the same day it was applied for: 56% of 5,717 permits issued from September 2024 to September 2026 were. After the permit, the typical finished remodel took about 6 months (180 days) from permit to final inspection (4,398 finished of 5,312 permits issued from September 2022 to September 2024; 17% had no final inspection on record by September 2026).

Same dayfrom application to permitMiddle half: same day to 14 days
6 monthsfrom permit to final inspectionMiddle half: 3 months to 11 months

The two steps

How long remodels take in San Francisco, in daysApplication to permit issued: median 0 days, middle half 0 to 14 days, 5,717 permits; Permit issued to final inspection: median 180 days, middle half 102 to 338 days, 4,398 permits.Application to permit issued: same dayPermit issued to final inspection: about 6 months03 mo6 mo9 mo
Bars show the median; the line through each bar spans the middle half of jobs. The second step starts where the typical permit wait ends. The two steps come from different groups of permits, so they are not added up.
The numbers behind the chart
StepMedianMiddle halfPermitsPermits issued
Application to permit issuedsame daysame day to 14 days5,717September 2024 to September 2026
Permit to final inspectionabout 6 monthsabout 3 months to about 11 months4,398September 2022 to September 2024

Remodeling contractors with the most jobs in San Francisco

RankContractorJobsContact
1Sure, Inc.
San Francisco, licensed 37 years
118
Call (415) 221-2888
2Mission Home Remodeling Inc
San Francisco, licensed 5 years
104
Visit website
3Edri Construction Inc
San Francisco, licensed 6 years
98
Visit website

See all 1,147 ranked remodeling contractors

Get quotes from up to 3 licensed remodeling contractors

Tell us about the job. Within one business day we email you up to 3 contractors with an active license who do this work near your ZIP code, and pass your request to them. You decide who to hire.

When do you want to start?

We got your request

Within one business day we will email you up to 3 licensed contractors who fit, and pass your request to them.

Permit wait by year issued

Year issuedJobsMedianMiddle half
2022723same daysame day to 17 days
20232,603same daysame day to 18 days
20242,633same daysame day to 17 days
20252,837same daysame day to 16 days
20262,233same daysame day to 11 days

Why it takes this long

  • 56% of permits were issued the day they were applied for, and 83% within 30 days (5,717 permits).
  • 68 more permits issued in those dates carry no application date and are left out of the permit wait.
  • The longer step is building and inspection: same day for the permit against about 6 months from permit to final, at the median.
  • 20% of finished jobs passed final inspection within 90 days of the permit.
  • Of the 5,312 permits issued from September 2022 to September 2024, 914 (17%) had no final inspection on record by September 2026. They may still be under way, dropped or never inspected; the records do not say which. They are left out of the build time; any of them that finishes will have taken more than two years, so counting them would make the typical time longer.

Days are counted between the dates on each city permit: filed_date, issued_date, completed_date. Median and middle half: half of the jobs took longer than the median; the middle half runs from the 25th to the 75th percentile. A figure is shown only when it rests on 30 or more permits. Kinds of work are sorted by the same rules as our contractor lists. Source: San Francisco Building, Electrical and Plumbing Permits (data.sf.gov i98e-djp9, ftty-kx6y, a6aw-rudh), read 2026-09-24. The same figures as data: remodel.json.