How long does a roofing permit take in San Francisco?

In San Francisco, the typical roofing permit was issued the same day it was applied for: 91% of 6,492 permits issued from September 2024 to September 2026 were. After the permit, the typical finished roofing job took 28 days from permit to final inspection (5,317 finished of 6,610 permits issued from September 2022 to September 2024; 20% had no final inspection on record by September 2026).

Same dayfrom application to permitMiddle half: same day to same day
28 daysfrom permit to final inspectionMiddle half: 13 days to 65 days

The two steps

How long roofing jobs take in San Francisco, in daysApplication to permit issued: median 0 days, middle half 0 to 0 days, 6,492 permits; Permit issued to final inspection: median 28 days, middle half 13 to 65 days, 5,317 permits.Application to permit issued: same dayPermit issued to final inspection: 28 days014 d28 d42 d56 d
Bars show the median; the line through each bar spans the middle half of jobs. The second step starts where the typical permit wait ends. The two steps come from different groups of permits, so they are not added up.
The numbers behind the chart
StepMedianMiddle halfPermitsPermits issued
Application to permit issuedsame daysame day to same day6,492September 2024 to September 2026
Permit to final inspection28 days13 days to 65 days5,317September 2022 to September 2024

Roofing contractors with the most jobs in San Francisco

RankContractorJobsContact
1Tom Lee Roofing Inc.
Daly City, licensed 29 years
903
Call (415) 333-5373
2Apollo Building & Roofing Group Inc.
Walnut Creek, licensed 5 years
575
Call (925) 860-3538
3American Standard Roofing Inc
San Francisco, licensed 10 years
344
Call (415) 671-0203

See all 303 ranked roofing contractors

Get quotes from up to 3 licensed roofing contractors

Tell us about the job. Within one business day we email you up to 3 contractors with an active license who do this work near your ZIP code, and pass your request to them. You decide who to hire.

When do you want to start?

We got your request

Within one business day we will email you up to 3 licensed contractors who fit, and pass your request to them.

Permit wait by year issued

Year issuedJobsMedianMiddle half
2022600same daysame day to same day
20233,179same daysame day to same day
20243,978same daysame day to same day
20253,678same daysame day to same day
20261,665same daysame day to same day

Why it takes this long

  • 91% of permits were issued the day they were applied for, and 99% within 30 days (6,492 permits).
  • 23 more permits issued in those dates carry no application date and are left out of the permit wait.
  • The longer step is building and inspection: same day for the permit against 28 days from permit to final, at the median.
  • 82% of finished jobs passed final inspection within 90 days of the permit.
  • Of the 6,610 permits issued from September 2022 to September 2024, 1,293 (20%) had no final inspection on record by September 2026. They may still be under way, dropped or never inspected; the records do not say which. They are left out of the build time; any of them that finishes will have taken more than two years, so counting them would make the typical time longer.

Days are counted between the dates on each city permit: filed_date, issued_date, completed_date. Median and middle half: half of the jobs took longer than the median; the middle half runs from the 25th to the 75th percentile. A figure is shown only when it rests on 30 or more permits. Kinds of work are sorted by the same rules as our contractor lists. Source: San Francisco Building, Electrical and Plumbing Permits (data.sf.gov i98e-djp9, ftty-kx6y, a6aw-rudh), read 2026-09-24. The same figures as data: roofing.json.