How long does a seismic retrofit permit take in San Francisco?
In San Francisco, the typical seismic retrofit permit took 16 days from application to issue, across 196 permits issued from September 2024 to September 2026. After the permit, the typical finished seismic retrofit took about 8 months (242 days) from permit to final inspection (274 finished of 366 permits issued from September 2022 to September 2024; 25% had no final inspection on record by September 2026).
8 monthsfrom permit to final inspectionMiddle half: 5 months to 15 months
The two steps
The numbers behind the chart
| Step | Median | Middle half | Permits | Permits issued |
|---|---|---|---|---|
| Application to permit issued | 16 days | same day to about 4 months | 196 | September 2024 to September 2026 |
| Permit to final inspection | about 8 months | about 5 months to about 15 months | 274 | September 2022 to September 2024 |
Seismic retrofit contractors with the most jobs in San Francisco
| Rank | Contractor | Jobs | Contact |
|---|---|---|---|
| 1 | Seismic Retrofitters Inc. San Francisco, licensed 28 years | Visit website | |
| 2 | Sft Construction Corp San Francisco, licensed 11 years | Call (415) 707-1046 | |
| 3 | Mulhall Construction Inc. Novato, licensed 18 years | Visit website |
See all 42 ranked seismic retrofit contractors
Get quotes from up to 3 licensed seismic retrofit contractors
Tell us about the job. Within one business day we email you up to 3 contractors with an active license who do this work near your ZIP code, and pass your request to them. You decide who to hire.
We got your request
Within one business day we will email you up to 3 licensed contractors who fit, and pass your request to them.
Permit wait by year issued
| Year issued | Jobs | Median | Middle half |
|---|---|---|---|
| 2022 | 53 | 76 days | 6 days to about 23 months |
| 2023 | 200 | 66 days | 12 days to about 9 months |
| 2024 | 146 | 64 days | 6 days to about 19 months |
| 2025 | 101 | 19 days | same day to about 3 months |
| 2026 | 62 | 8 days | same day to about 4 months |
Why it takes this long
- 26% of permits were issued the day they were applied for, and 57% within 30 days (196 permits).
- 1 more permits issued in those dates carry no application date and are left out of the permit wait.
- The longer step is building and inspection: 16 days for the permit against about 8 months from permit to final, at the median.
- 11% of finished jobs passed final inspection within 90 days of the permit.
- Of the 366 permits issued from September 2022 to September 2024, 92 (25%) had no final inspection on record by September 2026. They may still be under way, dropped or never inspected; the records do not say which. They are left out of the build time; any of them that finishes will have taken more than two years, so counting them would make the typical time longer.
Days are counted between the dates on each city permit: filed_date, issued_date, completed_date. Median and middle half: half of the jobs took longer than the median; the middle half runs from the 25th to the 75th percentile. A figure is shown only when it rests on 30 or more permits. Kinds of work are sorted by the same rules as our contractor lists. Source: San Francisco Building, Electrical and Plumbing Permits (data.sf.gov i98e-djp9, ftty-kx6y, a6aw-rudh), read 2026-09-24. The same figures as data: seismic-retrofit.json.