How long does a panel upgrade take in Seattle?
In Seattle, the typical finished panel upgrade took 37 days from permit to final inspection (4,746 finished of 5,236 permits issued from September 2022 to September 2024; 9% had no final inspection on record by September 2026).
The two steps
The numbers behind the chart
| Step | Median | Middle half | Permits | Permits issued |
|---|---|---|---|---|
| Permit to final inspection | 37 days | 12 days to about 4 months | 4,746 | September 2022 to September 2024 |
Panel upgrade electricians with the most jobs in Seattle
| Rank | Contractor | Jobs | Contact |
|---|---|---|---|
| 1 | Seatown Electric, Plumbing, Heating & Air Dba Seatown Services Mukilteo | Call (206) 905-4946 | |
| 2 | As You Wish Electric Seattle | Call (206) 423-1548 | |
| 3 | Greenwood Heating & Home Services Tukwila | Call (206) 784-1818 |
See all 333 ranked panel upgrade electricians
Get quotes from up to 3 licensed panel upgrade electricians
Tell us about the job. Within one business day we email you up to 3 contractors with an active license who do this work near your ZIP code, and pass your request to them. You decide who to hire.
We got your request
Within one business day we will email you up to 3 licensed contractors who fit, and pass your request to them.
Why it takes this long
- 70% of finished jobs passed final inspection within 90 days of the permit.
- Of the 5,236 permits issued from September 2022 to September 2024, 490 (9%) had no final inspection on record by September 2026. They may still be under way, dropped or never inspected; the records do not say which. They are left out of the build time; any of them that finishes will have taken more than two years, so counting them would make the typical time longer.
- The permit wait is not shown: 96% of 3,244 permits carry no application date, so the rest would not show the typical wait.
Days are counted between the dates on each city permit: applieddate, issueddate, completeddate. Median and middle half: half of the jobs took longer than the median; the middle half runs from the 25th to the 75th percentile. A figure is shown only when it rests on 30 or more permits. Kinds of work are sorted by the same rules as our contractor lists. Source: Seattle Building, Electrical and Trade Permits (data.seattle.gov 76t5-zqzr, c4tj-daue, c87v-5hwh), read 2026-09-24. The same figures as data: electrical-panel.json.