How long does a solar installation take in Seattle?

In Seattle, the typical finished solar installation took 43 days from permit to final inspection (1,875 finished of 2,085 permits issued from September 2022 to September 2024; 10% had no final inspection on record by September 2026).

43 daysfrom permit to final inspectionMiddle half: 24 days to 76 days

The two steps

How long solar installations take in Seattle, in daysPermit issued to final inspection: median 43 days, middle half 24 to 76 days, 1,875 permits.Permit issued to final inspection: 43 days030 d60 d
Bars show the median; the line through each bar spans the middle half of jobs.
The numbers behind the chart
StepMedianMiddle halfPermitsPermits issued
Permit to final inspection43 days24 days to 76 days1,875September 2022 to September 2024

Solar installers with the most jobs in Seattle

RankContractorJobsContact
1Puget Sound Solar
Seattle
501
Visit website
2A&r Solar Corp
Seattle
485
Call (206) 707-9937
3Sunergy Systems
Seattle
412
Call (206) 297-0086

See all 34 ranked solar installers

Get quotes from up to 3 licensed solar installers

Tell us about the job. Within one business day we email you up to 3 contractors with an active license who do this work near your ZIP code, and pass your request to them. You decide who to hire.

When do you want to start?

We got your request

Within one business day we will email you up to 3 licensed contractors who fit, and pass your request to them.

Why it takes this long

  • 81% of finished jobs passed final inspection within 90 days of the permit.
  • Of the 2,085 permits issued from September 2022 to September 2024, 210 (10%) had no final inspection on record by September 2026. They may still be under way, dropped or never inspected; the records do not say which. They are left out of the build time; any of them that finishes will have taken more than two years, so counting them would make the typical time longer.
  • The permit wait is not shown: 64% of 1,085 permits carry no application date, so the rest would not show the typical wait.

Days are counted between the dates on each city permit: applieddate, issueddate, completeddate. Median and middle half: half of the jobs took longer than the median; the middle half runs from the 25th to the 75th percentile. A figure is shown only when it rests on 30 or more permits. Kinds of work are sorted by the same rules as our contractor lists. Source: Seattle Building, Electrical and Trade Permits (data.seattle.gov 76t5-zqzr, c4tj-daue, c87v-5hwh), read 2026-09-24. The same figures as data: solar.json.