65 jobs on Austin permits, 2021 to 2026: 46 panel upgrades, 19 EV charger installations. 24th most panel upgrade permits of 327 contractors in Austin.

What the public records show

From the state's license records and the city's permits, one question at a time.

QuestionRecords showMark
Licensed?Texas electrical contractor license 29321, valid until Dec 8, 2026We matched it by the business name in the same city, Spicewood.Checks out
Jobs on record65 jobs on Austin permits, 2021 to 2026: 46 panel upgrades, 19 EV charger installations24th most panel upgrade permits of 327 contractors in Austin. That counts jobs, not quality.Our Austin permit records cover September 2021 to September 2026.

Records: City of Austin permits.

Cost and timing

Permit timeline

Across Austin, a panel upgrade permit stays open about 62 days, from permit to final inspection

This is not how long the crew works at your home: most of it is waiting for the inspection. Ask them how many days the work takes. Waiting for the permit adds about 6 days. How long panel upgrade jobs take.

Track record

25 jobs in the last 12 months, up from 15 the year before

Q4 2021: 1 jobQ1 2023: 3 jobsQ3 2023: 3 jobsQ4 2023: 8 jobsQ1 2024: 9 jobsQ3 2024: 1 jobQ4 2024: 1 jobQ1 2025: 5 jobsQ2 2025: 5 jobsQ3 2025: 6 jobsQ4 2025: 5 jobsQ1 2026: 11 jobsQ2 2026: 2 jobsQ3 2026: 5 jobsBusiest: 11 jobs20222023202420252026
Each bar is 3 months of permits. The tallest is 11 jobs, January to March 2026. Across Austin, all contractors together had 17% more panel upgrade jobs in the last 12 months than in the 12 months before.

Where they work most

  • 787386 jobs
  • 787465 jobs
  • 787595 jobs
  • 787485 jobs
  • 787325 jobs

Jobs by kind of work

Latest jobs

Permit values are what the contractor wrote on the permit form, not what the owner paid.

A row marked ×2 or more stands for that many similar jobs on one day in one ZIP code.

DateWorkZIPOn the permit form
Aug 26, 2026Panel upgradeReplace defective FP panel and old meter base with new 200A MB panel and 200R meter78725not stated
Aug 19, 2026Panel upgradeRepalcement of outdated 200A MB electrical panel and 200R meter base78746not stated
Aug 19, 2026Panel upgradeReplace defective meter base and panel78759not stated
Aug 7, 2026Panel upgradeReplacement of 200A MB panel and meter base78733not stated
Jul 13, 2026Panel upgradeReplace aging 100A main panel and meter base with new 100A Main Breaker Panel and 200R meter base…78746not stated
Jun 23, 2026Panel upgradeReplace existing aged 200A electrical service with new 200R meter base and 200A MCB Panel78703not stated
May 18, 2026Panel upgradeInstallation of new 200a overhead riser 200R Meter can and 200a Main Breaker Panel - Remove…78758not stated
Mar 12, 2026Panel upgradeReplace existing aged 200A overhead service with new 200A MB Panel 200R Meter Base and riser78746not stated
Mar 4, 2026Panel upgradeReplace aging meter base and FP panel with new 200R meter base and 200A MB Panel and riser78757not stated
Mar 3, 2026EV chargerInstallation of new 60A wall mounted EV charging unit - hardwired78717not stated
Feb 26, 2026EV chargerFurnish and install hardwired wall mounted EV charging unit and power in garage78717not stated
Feb 24, 2026Panel upgradeRemove existing rag riser and aged panel and install new 200R meter can and 200A MB Panel78746not stated
Feb 20, 2026Panel upgradeReplace existing FP panel and aging meter base with new 200R meter base and 200A MB panel78736not stated
Feb 18, 2026Panel upgradeRemove existing outdated meter and main electrical panel and install new 200R Meter Can and 200A MB…78759not stated
Feb 3, 2026Panel upgradeReplace existing outdated main panel and meter base with new 200a main breaker panel and 200R meter…78749not stated
Jan 28, 2026Panel upgradeReplace old meter and panel with new 200R Meter Base and 200A Main breaker panel78758not stated
Jan 9, 2026Panel upgradeReplace existing meter/panel with new 200a meter base and 200a main breaker panel78748not stated
Jan 6, 2026EV chargerInstallation of wall mounted EV charging unit - Hardwired78704not stated
Dec 26, 2025EV chargerInstallation of wall mounted EV charging unit - Hardwired78731not stated
Dec 4, 2025Panel upgrade (×2, same day)Installation of 2 - 200a Main Breaker Panels and 200a Meter Bases with Tap box and 400a Riser78750not stated
Dec 2, 2025Panel upgradeFurnish and install new 200a main breaker panel and new 200a meter base - Demo of existing aged…78732not stated
Oct 14, 2025Panel upgradeEmergency repair - Replace meter can with new 200R meter base and install new main breaker…78745not stated
Sep 30, 2025Panel upgradeElectrical Panel and Service Upgrades -Upgrade the main electrical service panel to 200 Amps when…78745not stated
Sep 23, 2025Panel upgradeReplace 200 amp main breaker exterior panel78738not stated
Sep 12, 2025Panel upgradeReplace aged 200A meter base and 200A main breaker panel with new 200A equipment78738not stated
Sep 5, 2025Panel upgradeUpgrade existing 125a underground service that has been red tagged to new 200a meter base and 200a…78759not stated
Aug 12, 2025Panel upgradeReplace indoor 60a main lug sub-panel and breakers & install whole home surge protection at main…78732not stated
Aug 6, 2025Panel upgradeRequest to Disconnect - Replace existing outdated 200amp 40 ckt Main Breaker Panel with new 200amp…78735not stated
May 29, 2025Panel upgradeReplace existing 200a overhead electrical service and interior sub-panel78759not stated
May 29, 2025EV chargerReplace existing 200a overhead electrical service and interior sub-panel78759not stated
May 27, 2025Panel upgradeReplace existing meter base and Federal Pacific Panel with new 200R Meter Base and 200a MB Panel78727not stated
May 21, 2025Panel upgradeReplacement of aging equipment and installation of new 200a Main Breaker Panel and 200R Meter Base78730not stated
Apr 16, 2025Panel upgradeNo details on the permit78748not stated
Mar 27, 2025Panel upgradeUpgrade 200a service to new 350a Main panel and 320a Meter Base with new riser - Relocate panel78756not stated
Mar 13, 2025Panel upgradeReplace exterior 125a service with new 125a Main Breaker panel and new 200a meter base78753not stated
Mar 12, 2025Panel upgradeUpgrade existing 100a underground main panel and meter base to 200a78727not stated
Feb 27, 2025EV chargerInstallation of GFCI protected 240v outlet for EV charger78748not stated
Feb 19, 2025Panel upgradeAmend to the CDP program - Request to disconnect Replace damaged 200a main electrical panel78732not stated
Dec 31, 2024EV chargerNo details on the permit78750not stated
Aug 30, 2024Panel upgradeExpress - Drywall removal and repair with painting in living room/ dinning room78704not stated

What to ask before you hire

About Magnify Electric

  • Ask what the warranty covers and for how long, in writing.
  • Search their name on the Better Business Bureau site, and read their reviews.

Worth asking any panel upgrade electrician

  • Can you show me proof of liability insurance and your bond?
  • What size panel, and does the utility need to change the service to my house?
  • Who arranges the power shutoff with the utility?
  • Who pulls the permit, and who meets the inspector?

Get a quote from Magnify Electric

Five quick questions. We pass your request to Magnify Electric.

You decide who to hire. Your details go only to the contractors you pick. How we use your details

1. Where is the job?

We match contractors who work near it. We never ask for your street address.

2. What do you need?

Pick any that fit.

3. When do you want to start?
4. What is your rough budget?

A range is fine. It helps contractors reply with a real number.

5. Where should we send it?

Your contact details go only to who you pick here.

Sent. We have your request.

We pass it to Magnify Electric. Replies usually come within a few days.

Your job room keeps the request, your photos and every reply in one place, with an assistant that checks prices against city permits. Keep its link: it is the key to your job.

Open your job room

More panel upgrade electricians near 78738 and 78746

See all 327 panel upgrade electricians in Austin, ranked by jobs

Run this business? Claim this page to get requests by email and reply to homeowners here.

Is this your business? Correct a record or add your warranty terms. It is free.

We check every change before it goes on the page, usually within a week, and may call to confirm you run the business.