How long does a panel upgrade permit take in Austin?
In Austin, the typical panel upgrade permit took 6 days from application to issue, across 2,623 permits issued from September 2024 to September 2026. After the permit, the typical finished panel upgrade took 62 days from permit to final inspection (2,294 finished of 2,539 permits issued from September 2022 to September 2024; 10% had no final inspection on record by September 2026).
62 daysfrom permit to final inspectionMiddle half: 20 days to 5 months
The two steps
The numbers behind the chart
| Step | Median | Middle half | Permits | Permits issued |
|---|---|---|---|---|
| Application to permit issued | 6 days | 3 days to 11 days | 2,623 | September 2024 to September 2026 |
| Permit to final inspection | 62 days | 20 days to about 5 months | 2,294 | September 2022 to September 2024 |
Panel upgrade electricians with the most jobs in Austin
| Rank | Contractor | Jobs | Contact |
|---|---|---|---|
| 1 | Jonestown Electrical Solutions LLC | Get a quote | |
| 2 | Salt Light & Electric | Get a quote | |
| 3 | Service Company of San Antonio LLC Dba Mr Electric of Austin | Get a quote |
See all 327 ranked panel upgrade electricians
Get quotes from up to 3 panel upgrade electricians
Tell us about the job. Within one business day we email you up to 3 contractors who do this work near your ZIP code, and pass your request to them. You decide who to hire.
We got your request
Within one business day we will email you up to 3 contractors who fit, and pass your request to them.
Permit wait by year issued
| Year issued | Jobs | Median | Middle half |
|---|---|---|---|
| 2022 | 316 | 4 days | 2 days to 9 days |
| 2023 | 1,362 | 5 days | 2 days to 10 days |
| 2024 | 1,128 | 6 days | 3 days to 12 days |
| 2025 | 1,254 | 6 days | 3 days to 12 days |
| 2026 | 1,102 | 4 days | 2 days to 8 days |
Why it takes this long
- 2% of permits were issued the day they were applied for, and 91% within 30 days (2,623 permits).
- 2 more permits issued in those dates carry no application date and are left out of the permit wait.
- The longer step is building and inspection: 6 days for the permit against 62 days from permit to final, at the median.
- 60% of finished jobs passed final inspection within 90 days of the permit.
- Of the 2,539 permits issued from September 2022 to September 2024, 245 (10%) had no final inspection on record by September 2026. They may still be under way, dropped or never inspected; the records do not say which. They are left out of the build time; any of them that finishes will have taken more than two years, so counting them would make the typical time longer.
Days are counted between the dates on each city permit: applieddate, issue_date, completed_date. Median and middle half: half of the jobs took longer than the median; the middle half runs from the 25th to the 75th percentile. A figure is shown only when it rests on 30 or more permits. Kinds of work are sorted by the same rules as our contractor lists. Source: Austin Issued Construction Permits (data.austintexas.gov 3syk-w9eu), read 2026-09-24. The same figures as data: electrical-panel.json.