How long does a roofing permit take in Chicago?
In Chicago, the typical roofing permit took 1 day from application to issue, across 1,969 permits issued from September 2024 to September 2026.
The two steps
The numbers behind the chart
| Step | Median | Middle half | Permits | Permits issued |
|---|---|---|---|---|
| Application to permit issued | 1 day | same day to 4 days | 1,969 | September 2024 to September 2026 |
Roofing contractors with the most jobs in Chicago
| Rank | Contractor | Jobs | Contact |
|---|---|---|---|
| 1 | Magdan Construction Inc | Get a quote | |
| 2 | Holman and Nachtwey Company | Get a quote | |
| 3 | Pacc Construction LLC dba Pacc Building Group LLC | Get a quote |
See all 252 ranked roofing contractors
Get quotes from up to 3 roofing contractors
Tell us about the job. Within one business day we email you up to 3 contractors who do this work near your ZIP code, and pass your request to them. You decide who to hire.
We got your request
Within one business day we will email you up to 3 contractors who fit, and pass your request to them.
Permit wait by year issued
| Year issued | Jobs | Median | Middle half |
|---|---|---|---|
| 2024 | 193 | 1 day | same day to 8 days |
| 2025 | 915 | 1 day | same day to 5 days |
| 2026 | 861 | same day | same day to 3 days |
Why it takes this long
- 48% of permits were issued the day they were applied for, and 96% within 30 days (1,969 permits).
- The time to final inspection is not shown: the city's permit data has no final inspection date.
Days are counted between the dates on each city permit: application_start_date, issue_date. Median and middle half: half of the jobs took longer than the median; the middle half runs from the 25th to the 75th percentile. A figure is shown only when it rests on 30 or more permits. Kinds of work are sorted by the same rules as our contractor lists. Source: Chicago Building Permits (data.cityofchicago.org ydr8-5enu), read 2026-09-24. The same figures as data: roofing.json.