How long does an ADU permit take in Nashville?

In Nashville, the typical ADU permit took 40 days from application to issue, across 553 permits issued from September 2024 to September 2026.

40 daysfrom application to permitMiddle half: 19 days to 79 days

The two steps

How long ADUs take in Nashville, in daysApplication to permit issued: median 40 days, middle half 19 to 79 days, 553 permits.Application to permit issued: 40 days030 d60 d
Bars show the median; the line through each bar spans the middle half of jobs.
The numbers behind the chart
StepMedianMiddle halfPermitsPermits issued
Application to permit issued40 days19 days to 79 days553September 2024 to September 2026

ADU builders with the most jobs in Nashville

RankContractorJobsContact
1Palmetto Construction LLC
21
Get a quote
2Regent Homes
18
Get a quote
3Affordable Building Concepts
16
Visit website

See all 59 ranked ADU builders

Get quotes from up to 3 ADU builders

Five quick questions. We send your request to up to 3 contractors who work near you, and email you who they are.

You decide who to hire. Your details go only to the contractors you pick. How we use your details

1. Where is the job?

We match contractors who work near it. We never ask for your street address.

2. What do you need?

Pick any that fit.

3. When do you want to start?
4. What is your rough budget?

A range is fine. It helps contractors reply with a real number.

5. Where should we send it?

Your contact details go only to who you pick here.

Sent. We have your request.

Over the next few days we email you up to 3 contractors who fit, and pass your request to them. Replies usually come within a few days.

Your job room keeps the request, your photos and every reply in one place, with an assistant that checks prices against city permits. Keep its link: it is the key to your job.

Open your job room

Permit wait by year issued

Year issuedJobsMedianMiddle half
20233661 days18 days to about 4 months
202421646 days27 days to 82 days
202524142 days21 days to 82 days
202626438 days16 days to 78 days

Why it takes this long

  • 1% of permits were issued the day they were applied for, and 41% within 30 days (553 permits).
  • The time to final inspection is not shown: the city's permit data has no final inspection date.

Days are counted between the dates on each city permit: Date_Entered, Date_Issued. Median and middle half: half of the jobs took longer than the median; the middle half runs from the 25th to the 75th percentile. A figure is shown only when it rests on 30 or more permits. Kinds of work are sorted by the same rules as our contractor lists. Source: Metro Nashville Building Permits Issued (ArcGIS Building_Permits_Issued_2), read 2026-09-24. The same figures as data: adu.json.