How long does an ADU permit take in Nashville?

In Nashville, the typical ADU permit took 40 days from application to issue, across 553 permits issued from September 2024 to September 2026.

40 daysfrom application to permitMiddle half: 19 days to 79 days

The two steps

How long ADUs take in Nashville, in daysApplication to permit issued: median 40 days, middle half 19 to 79 days, 553 permits.Application to permit issued: 40 days030 d60 d
Bars show the median; the line through each bar spans the middle half of jobs.
The numbers behind the chart
StepMedianMiddle halfPermitsPermits issued
Application to permit issued40 days19 days to 79 days553September 2024 to September 2026

ADU builders with the most jobs in Nashville

RankContractorJobsContact
1Palmetto Construction LLC
21
Get a quote
2Regent Homes
18
Get a quote
3Affordable Building Concepts
16
Get a quote

See all 59 ranked ADU builders

Get quotes from up to 3 ADU builders

Tell us about the job. Within one business day we email you up to 3 contractors who do this work near your ZIP code, and pass your request to them. You decide who to hire.

When do you want to start?

We got your request

Within one business day we will email you up to 3 contractors who fit, and pass your request to them.

Permit wait by year issued

Year issuedJobsMedianMiddle half
20233661 days18 days to about 4 months
202421646 days27 days to 82 days
202524142 days21 days to 82 days
202626438 days16 days to 78 days

Why it takes this long

  • 1% of permits were issued the day they were applied for, and 41% within 30 days (553 permits).
  • The time to final inspection is not shown: the city's permit data has no final inspection date.

Days are counted between the dates on each city permit: Date_Entered, Date_Issued. Median and middle half: half of the jobs took longer than the median; the middle half runs from the 25th to the 75th percentile. A figure is shown only when it rests on 30 or more permits. Kinds of work are sorted by the same rules as our contractor lists. Source: Metro Nashville Building Permits Issued (ArcGIS Building_Permits_Issued_2), read 2026-09-24. The same figures as data: adu.json.