How long does a pool permit take in Nashville?
In Nashville, the typical pool permit took 31 days from application to issue, across 184 permits issued from September 2024 to September 2026.
The two steps
The numbers behind the chart
| Step | Median | Middle half | Permits | Permits issued |
|---|---|---|---|---|
| Application to permit issued | 31 days | 17 days to 61 days | 184 | September 2024 to September 2026 |
Pool builders with the most jobs in Nashville
| Rank | Contractor | Jobs | Contact |
|---|---|---|---|
| 1 | Southern Edge Construction LLC | Get a quote | |
| 2 | Sparks, Kevin Signature Pools, LLC | Get a quote | |
| 3 | Superior Capital Llc | Get a quote |
See all 20 ranked pool builders
Get quotes from up to 3 pool builders
Tell us about the job. Within one business day we email you up to 3 contractors who do this work near your ZIP code, and pass your request to them. You decide who to hire.
We got your request
Within one business day we will email you up to 3 contractors who fit, and pass your request to them.
Permit wait by year issued
| Year issued | Jobs | Median | Middle half |
|---|---|---|---|
| 2024 | 97 | 48 days | 25 days to about 3 months |
| 2025 | 85 | 31 days | 20 days to 56 days |
| 2026 | 82 | 30 days | 14 days to 61 days |
Why it takes this long
- 2% of permits were issued the day they were applied for, and 49% within 30 days (184 permits).
- The time to final inspection is not shown: the city's permit data has no final inspection date.
Days are counted between the dates on each city permit: Date_Entered, Date_Issued. Median and middle half: half of the jobs took longer than the median; the middle half runs from the 25th to the 75th percentile. A figure is shown only when it rests on 30 or more permits. Kinds of work are sorted by the same rules as our contractor lists. Source: Metro Nashville Building Permits Issued (ArcGIS Building_Permits_Issued_2), read 2026-09-24. The same figures as data: pool.json.