How long does a remodel permit take in Nashville?
In Nashville, the typical remodel permit took 9 days from application to issue, across 373 permits issued from September 2024 to September 2026.
The two steps
The numbers behind the chart
| Step | Median | Middle half | Permits | Permits issued |
|---|---|---|---|---|
| Application to permit issued | 9 days | 4 days to 21 days | 373 | September 2024 to September 2026 |
Remodeling contractors with the most jobs in Nashville
| Rank | Contractor | Jobs | Contact |
|---|---|---|---|
| 1 | The Dan Company | Get a quote | |
| 2 | Borntrager Homes Inc | Get a quote | |
| 3 | Huffine First Service | Get a quote |
See all 44 ranked remodeling contractors
Get quotes from up to 3 remodeling contractors
Tell us about the job. Within one business day we email you up to 3 contractors who do this work near your ZIP code, and pass your request to them. You decide who to hire.
We got your request
Within one business day we will email you up to 3 contractors who fit, and pass your request to them.
Permit wait by year issued
| Year issued | Jobs | Median | Middle half |
|---|---|---|---|
| 2023 | 41 | 14 days | 9 days to 36 days |
| 2024 | 181 | 14 days | 5 days to 27 days |
| 2025 | 177 | 10 days | 5 days to 21 days |
| 2026 | 146 | 9 days | 4 days to 22 days |
Why it takes this long
- 4% of permits were issued the day they were applied for, and 83% within 30 days (373 permits).
- The time to final inspection is not shown: the city's permit data has no final inspection date.
Days are counted between the dates on each city permit: Date_Entered, Date_Issued. Median and middle half: half of the jobs took longer than the median; the middle half runs from the 25th to the 75th percentile. A figure is shown only when it rests on 30 or more permits. Kinds of work are sorted by the same rules as our contractor lists. Source: Metro Nashville Building Permits Issued (ArcGIS Building_Permits_Issued_2), read 2026-09-24. The same figures as data: remodel.json.