How long does a remodel permit take in Nashville?

In Nashville, the typical remodel permit took 9 days from application to issue, across 373 permits issued from September 2024 to September 2026.

9 daysfrom application to permitMiddle half: 4 days to 21 days

The two steps

How long remodels take in Nashville, in daysApplication to permit issued: median 9 days, middle half 4 to 21 days, 373 permits.Application to permit issued: 9 days07 d14 d21 d
Bars show the median; the line through each bar spans the middle half of jobs.
The numbers behind the chart
StepMedianMiddle halfPermitsPermits issued
Application to permit issued9 days4 days to 21 days373September 2024 to September 2026

Remodeling contractors with the most jobs in Nashville

RankContractorJobsContact
1The Dan Company
23
Visit website
2Borntrager Homes Inc
17
Visit website
3Huffine First Service
17
Get a quote

See all 44 ranked remodeling contractors

Get quotes from up to 3 remodeling contractors

Five quick questions. We send your request to up to 3 contractors who work near you, and email you who they are.

You decide who to hire. Your details go only to the contractors you pick. How we use your details

1. Where is the job?

We match contractors who work near it. We never ask for your street address.

2. What do you need?

Pick any that fit.

3. When do you want to start?
4. What is your rough budget?

A range is fine. It helps contractors reply with a real number.

5. Where should we send it?

Your contact details go only to who you pick here.

Sent. We have your request.

Over the next few days we email you up to 3 contractors who fit, and pass your request to them. Replies usually come within a few days.

Your job room keeps the request, your photos and every reply in one place, with an assistant that checks prices against city permits. Keep its link: it is the key to your job.

Open your job room

Permit wait by year issued

Year issuedJobsMedianMiddle half
20234114 days9 days to 36 days
202418114 days5 days to 27 days
202517710 days5 days to 21 days
20261469 days4 days to 22 days

Why it takes this long

  • 4% of permits were issued the day they were applied for, and 83% within 30 days (373 permits).
  • The time to final inspection is not shown: the city's permit data has no final inspection date.

Days are counted between the dates on each city permit: Date_Entered, Date_Issued. Median and middle half: half of the jobs took longer than the median; the middle half runs from the 25th to the 75th percentile. A figure is shown only when it rests on 30 or more permits. Kinds of work are sorted by the same rules as our contractor lists. Source: Metro Nashville Building Permits Issued (ArcGIS Building_Permits_Issued_2), read 2026-09-24. The same figures as data: remodel.json.