How long does a remodel permit take in Nashville?

In Nashville, the typical remodel permit took 9 days from application to issue, across 373 permits issued from September 2024 to September 2026.

9 daysfrom application to permitMiddle half: 4 days to 21 days

The two steps

How long remodels take in Nashville, in daysApplication to permit issued: median 9 days, middle half 4 to 21 days, 373 permits.Application to permit issued: 9 days07 d14 d21 d
Bars show the median; the line through each bar spans the middle half of jobs.
The numbers behind the chart
StepMedianMiddle halfPermitsPermits issued
Application to permit issued9 days4 days to 21 days373September 2024 to September 2026

Remodeling contractors with the most jobs in Nashville

RankContractorJobsContact
1The Dan Company
23
Get a quote
2Borntrager Homes Inc
17
Get a quote
3Huffine First Service
17
Get a quote

See all 44 ranked remodeling contractors

Get quotes from up to 3 remodeling contractors

Tell us about the job. Within one business day we email you up to 3 contractors who do this work near your ZIP code, and pass your request to them. You decide who to hire.

When do you want to start?

We got your request

Within one business day we will email you up to 3 contractors who fit, and pass your request to them.

Permit wait by year issued

Year issuedJobsMedianMiddle half
20234114 days9 days to 36 days
202418114 days5 days to 27 days
202517710 days5 days to 21 days
20261469 days4 days to 22 days

Why it takes this long

  • 4% of permits were issued the day they were applied for, and 83% within 30 days (373 permits).
  • The time to final inspection is not shown: the city's permit data has no final inspection date.

Days are counted between the dates on each city permit: Date_Entered, Date_Issued. Median and middle half: half of the jobs took longer than the median; the middle half runs from the 25th to the 75th percentile. A figure is shown only when it rests on 30 or more permits. Kinds of work are sorted by the same rules as our contractor lists. Source: Metro Nashville Building Permits Issued (ArcGIS Building_Permits_Issued_2), read 2026-09-24. The same figures as data: remodel.json.