How long does an EV charger permit take in San Francisco?
In San Francisco, the typical EV charger permit was issued the same day it was applied for: 100% of 1,088 permits issued from September 2024 to September 2026 were. After the permit, the typical finished EV charger installation took 27 days from permit to final inspection (1,036 finished of 1,212 permits issued from September 2022 to September 2024; 15% had no final inspection on record by September 2026).
27 daysfrom permit to final inspectionMiddle half: 9 days to 72 days
The two steps
The numbers behind the chart
| Step | Median | Middle half | Permits | Permits issued |
|---|---|---|---|---|
| Application to permit issued | same day | same day to same day | 1,088 | September 2024 to September 2026 |
| Permit to final inspection | 27 days | 9 days to 72 days | 1,036 | September 2022 to September 2024 |
EV charger installers with the most jobs in San Francisco
| Rank | Contractor | Jobs | Contact |
|---|---|---|---|
| 1 | Coil Inc San Francisco, licensed 24 years | Visit website | |
| 2 | Wells Electrical, Inc San Francisco, licensed 33 years | Visit website | |
| 3 | Tomtech licensed 28 years | Call (818) 427-7464 |
See all 129 ranked EV charger installers
Get quotes from up to 3 licensed EV charger installers
Tell us about the job. Within one business day we email you up to 3 contractors with an active license who do this work near your ZIP code, and pass your request to them. You decide who to hire.
We got your request
Within one business day we will email you up to 3 licensed contractors who fit, and pass your request to them.
Permit wait by year issued
| Year issued | Jobs | Median | Middle half |
|---|---|---|---|
| 2022 | 138 | same day | same day to same day |
| 2023 | 730 | same day | same day to same day |
| 2024 | 449 | same day | same day to same day |
| 2025 | 521 | same day | same day to same day |
| 2026 | 462 | same day | same day to same day |
Why it takes this long
- 100% of permits were issued the day they were applied for, and 100% within 30 days (1,088 permits).
- The longer step is building and inspection: same day for the permit against 27 days from permit to final, at the median.
- 79% of finished jobs passed final inspection within 90 days of the permit.
- Of the 1,212 permits issued from September 2022 to September 2024, 176 (15%) had no final inspection on record by September 2026. They may still be under way, dropped or never inspected; the records do not say which. They are left out of the build time; any of them that finishes will have taken more than two years, so counting them would make the typical time longer.
Days are counted between the dates on each city permit: filed_date, issued_date, completed_date. Median and middle half: half of the jobs took longer than the median; the middle half runs from the 25th to the 75th percentile. A figure is shown only when it rests on 30 or more permits. Kinds of work are sorted by the same rules as our contractor lists. Source: San Francisco Building, Electrical and Plumbing Permits (data.sf.gov i98e-djp9, ftty-kx6y, a6aw-rudh), read 2026-09-24. The same figures as data: ev-charger.json.