49 jobs on Austin permits, 2021 to 2026: 34 panel upgrades, 14 EV charger installations, 1 solar installation. 31st most panel upgrade permits of 327 contractors in Austin.

What the public records show

From the state's license records and the city's permits, one question at a time.

QuestionRecords showMark
Licensed?Texas electrical contractor license 34992, valid until Mar 8, 2027We matched it by the phone on their permits.Checks out
Jobs on record49 jobs on Austin permits, 2021 to 2026: 34 panel upgrades, 14 EV charger installations, 1 solar installation31st most panel upgrade permits of 327 contractors in Austin. That counts jobs, not quality.Our Austin permit records cover September 2021 to September 2026.

Records: City of Austin permits.

Cost and timing

Permit timeline

Across Austin, a panel upgrade permit stays open about 62 days, from permit to final inspection

This is not how long the crew works at your home: most of it is waiting for the inspection. Ask them how many days the work takes. Waiting for the permit adds about 6 days. How long panel upgrade jobs take.

Track record

12 jobs in the last 12 months, down from 15 the year before

Q3 2021: 1 jobQ4 2022: 1 jobQ2 2023: 2 jobsQ4 2023: 5 jobsQ1 2024: 2 jobsQ2 2024: 6 jobsQ3 2024: 5 jobsQ4 2024: 7 jobsQ1 2025: 6 jobsQ2 2025: 2 jobsQ4 2025: 1 jobQ1 2026: 5 jobsQ2 2026: 2 jobsQ3 2026: 4 jobsBusiest: 7 jobs20222023202420252026
Each bar is 3 months of permits. The tallest is 7 jobs, October to December 2024. Across Austin, all contractors together had 17% more panel upgrade jobs in the last 12 months than in the 12 months before.

Where they work most

  • 787299 jobs
  • 787316 jobs
  • 787504 jobs
  • 787594 jobs
  • 787573 jobs

Jobs by kind of work

Latest jobs

Permit values are what the contractor wrote on the permit form, not what the owner paid.

DateWorkZIPOn the permit form
Sep 22, 2026Panel upgradePEC power provider78717not stated
Aug 10, 2026Panel upgradeProperty has pedestal with meter and main breaker at the street78750not stated
Jul 14, 2026Panel upgradeReplace existing 200 amp main panel and meter with new main panel and meter to current code78757not stated
Jul 10, 2026Panel upgradeNot touching PEC meter78750not stated
Jun 26, 2026Panel upgradeReplace existing meter and panel with new 225 amp78732not stated
May 2, 2026Panel upgradeRequest to disconnect replacing existing 200 amp main panel with a new 200 amp automatic transfer…78731not stated
Mar 24, 2026EV chargerHardwire EV charger in garage78759not stated
Feb 6, 2026Panel upgradeInstall EV charger 10 from main panel78731not stated
Feb 6, 2026EV chargerInstall EV charger 10 from main panel78731not stated
Jan 27, 2026Panel upgradeRequest to disconnect Not touching / leaving line side conductors and meter can78729not stated
Jan 27, 2026EV chargerRequest to disconnect Not touching / leaving line side conductors and meter can78729not stated
Dec 18, 2025Panel upgradeReuse existing condenser wire run new wiring for air handler from attic back to panel78750not stated
Apr 21, 2025Solar, 20 kWInstall 20 KW Kohler generator78730not stated
Apr 14, 2025Panel upgradeRequest to disconnect Update existing overhead 200amp meter loop including meter panel mast…78729not stated
Mar 21, 2025Panel upgradeRequest to disconnect leave existing 200 and meter replace main panel with new 200 amp78738not stated
Mar 6, 2025Panel upgradeRequest to disconnect Replace service with new 200 A meter and panel78759not stated
Mar 5, 2025Panel upgradeRequest to disconnect replacing two main panels with automatic transfer switch load center combos78746not stated
Feb 22, 2025Panel upgradeRequest to disconnect leave existing 200 amp meter and replace main panel with like78732not stated
Feb 19, 2025EV chargerAdd EV 14-50 gfci plug in garage78729not stated
Feb 3, 2025Panel upgradeRequest to disconnect Not touching existing 200 amp meter can78733not stated
Oct 23, 2024EV chargerAdd 2 EV charging stations on front of house78729not stated
Oct 22, 2024Panel upgradeAddition/remodel78731not stated
Oct 16, 2024Panel upgradeMain service Replace w/ new 200 amp meter and panel78729not stated
Oct 16, 2024EV chargerMain service Replace w/ new 200 amp meter and panel78729not stated
Oct 7, 2024Panel upgradeRequest to disconnect cut AE wires and secure78745not stated
Oct 4, 2024Panel upgradeEV charger under panel78749not stated
Oct 4, 2024EV chargerEV charger under panel78749not stated
Aug 12, 2024Panel upgrade, 26 kWRequest to disconnect Leave existing 200 amp meter78746not stated
Jul 31, 2024Panel upgrade, 22 kWRequest to Disconnect 200 amp meter and panel upgrade78745not stated
Jul 31, 2024EV charger, 22 kWRequest to Disconnect 200 amp meter and panel upgrade78745not stated
Jul 1, 2024Panel upgradeRequest to disconnect Leave AE wires attached to riser replace main conductors 200 amp meter can…78759not stated
Jul 1, 2024EV chargerAdd EV 60amp charger78752not stated
Jun 21, 2024Panel upgradeReplace meter with new78730not stated
May 15, 2024Panel upgradeRequest to disconnect78728not stated
May 10, 2024Panel upgradeRequest to disconnect leave existing mast at overhead service replace meter can and main panel to…78722not stated
May 8, 2024Panel upgradeRequest to disconnect leave existing meter install new 300 amp automatic transfer switch re-feed…78732not stated
Apr 29, 2024Panel upgradeRequest to disconnect Meter location slide to the left roughly 16 new riser penetrate the roof78757not stated
Apr 17, 2024Panel upgradeRequest to disconnect Not touching meter installing new 300 amp ATS to the left of existing 300 amp…78731not stated
Mar 19, 2024Panel upgradeNo details on the permit78729not stated
Jan 29, 2024Panel upgrade*request to disconnect* overhead service Requesting to leave existing one point attachment and 2…78751not stated

What to ask before you hire

About Bear Electric LLC

  • Ask what the warranty covers and for how long, in writing.
  • Search their name on the Better Business Bureau site, and read their reviews.

Worth asking any panel upgrade electrician

  • Can you show me proof of liability insurance and your bond?
  • What size panel, and does the utility need to change the service to my house?
  • Who arranges the power shutoff with the utility?
  • Who pulls the permit, and who meets the inspector?

Get a quote from Bear Electric LLC

Five quick questions. We pass your request to Bear Electric LLC.

You decide who to hire. Your details go only to the contractors you pick. How we use your details

1. Where is the job?

We match contractors who work near it. We never ask for your street address.

2. What do you need?

Pick any that fit.

3. When do you want to start?
4. What is your rough budget?

A range is fine. It helps contractors reply with a real number.

5. Where should we send it?

Your contact details go only to who you pick here.

Sent. We have your request.

We pass it to Bear Electric LLC. Replies usually come within a few days.

Your job room keeps the request, your photos and every reply in one place, with an assistant that checks prices against city permits. Keep its link: it is the key to your job.

Open your job room

More panel upgrade electricians near 78729 and 78731

See all 327 panel upgrade electricians in Austin, ranked by jobs

Run this business? Claim this page to get requests by email and reply to homeowners here.

Is this your business? Correct a record or add your warranty terms. It is free.

We check every change before it goes on the page, usually within a week, and may call to confirm you run the business.